Delays by Utility Owners. 6.8.5.1 DB Contractor shall bear 100% of the risk of Critical Path delays caused by a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which has been executed by DB Contractor and such Utility Owner.
Appears in 4 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Delays by Utility Owners. 6.8.5.1 6.8.5.1. DB Contractor shall bear 100% of the risk of Critical Path delays caused by a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which has been executed by DB Contractor and such Utility Owner.
Appears in 3 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Delays by Utility Owners. 6.8.5.1 6.7.5.1. DB Contractor shall bear 100% of the risk of Critical Path delays caused by a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which has been executed by DB Contractor and such Utility Owner.
Appears in 3 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Delays by Utility Owners. 6.8.5.1 6.8.6.1. DB Contractor shall bear 100% of the risk of Critical Path delays caused by (a) a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which has been executed by DB Contractor and such Utility Owner.Owner or
Appears in 1 contract
Samples: Design Build Agreement
Delays by Utility Owners. 6.8.5.1 DB Contractor shall bear 100% of the risk of Critical Path delays caused by a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which that has been executed by DB Contractor and such Utility Owner.
Appears in 1 contract
Samples: Design Build Agreement