Common use of Damages Calculation Clause in Contracts

Damages Calculation. Each Party acknowledges and agrees that: (a) the damages PacifiCorp would incur due to Seller’s delay in achieving Commercial Operation by the Scheduled Commercial Operation Date are difficult or impossible to predict with certainty; (b) it is impractical and difficult to assess actual damages in these circumstances; and, therefore,

Appears in 3 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Damages Calculation. Each Party acknowledges and agrees that: (a) the damages PacifiCorp would incur due to Seller’s delay in achieving Commercial Operation by the Scheduled Commercial Operation Date are difficult or impossible to predict with certainty; (b) it is impractical and difficult to assess actual damages in these circumstances; and, therefore,, (c) Delay Damages as agreed to by the Parties are a fair and reasonable calculation of damages and not a penalty.

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Damages Calculation. Each Party acknowledges and agrees that: (a) the damages PacifiCorp would incur due to Seller’s delay in achieving Commercial Operation by the Scheduled Commercial Operation Date are difficult or impossible to predict with certainty; (b) it is impractical and difficult to assess actual damages in these circumstances; and, therefore,therefore,‌

Appears in 1 contract

Sources: Energy Storage Agreement