Critical Path. A sequence of Work activities shown in the Baseline Schedule, which establish the total duration of time for the construction of the Work, and if such activities were delayed or extended, would change the construction duration established in the accepted Baseline Schedule.
Appears in 1 contract
Sources: Construction Agreement
Critical Path. A a sequence of Work activities shown in the Baseline Scheduleactivities, which establish the total duration of time for the construction of the WorkProject, and if such activities any activity along the critical path were delayed or extended, would change the construction duration established in the accepted approved Baseline Schedule.
Appears in 1 contract
Sources: Design Build Agreement