Common use of Critical Path Clause in Contracts

Critical Path. 1.9.1. The term “critical path” as used in the Contract Documents shall mean the construction activity schedule that establishes the minimum overall Project duration.

Appears in 5 contracts

Sources: Master Site Lease, Master Site Lease, Master Site Lease

Critical Path. 1.9.1. The term “critical path” as used in the Contract Documents shall mean the construction activity network of schedule activities that establishes the minimum overall Project duration.

Appears in 1 contract

Sources: Master Site Lease