Correct Setting Out. 7.2.1. Subject to clause 7.1, the Contractor is responsible for the correct setting out of the Works and must provide all necessary equipment and materials for so doing.
7.2.2. The Contractor shall preserve and maintain all Datum Points in their correct positions. If any Datum Point is disturbed or obliterated, the Contractor shall immediately notify the Company.
7.2.3. The Contractor, at its own expense, must remedy any error which arises from the inaccurate setting out of the Works. The Company shall have the right to check the Contractor’s setting out but neither its doing so nor its failure to do so will absolve the Contractor from its responsibility for correct setting out.