Contract Deviations. 1. Any changes to the work will in any case result in additional work if: a. there is a change in the design, specifications or contract documents; b. the information provided by The Customer does not correspond to the actual situation; c. estimated quantities deviate by more than 5%. 2. Additional work will be calculated on the basis of the price-determining factors applicable at the time the additional work is performed. The Customer is obliged topaythe price of theadditional work at 2Connect's first request, without suspension or settlement (not even in the case of less work). 3. Changes to the work will only result in less work if/when: a. 2Connect has agreed in writing not to carry out the contract reduction; b. The contract reduction actually results in a cost saving for 2Connect and 2Connect has confirmed this to The Customer in writing; 4. Contract reductions are calculated on the basis of the amounts budgeted by 2Connect and only include savings of materials and external costs, under no circumstances savings of internal costs of 2Connect (such as staff costs).
Appears in 1 contract
Sources: Terms and Conditions
Contract Deviations. 1. Any changes to the work will in any case result in additional work if:
a. there is a change in the design, specifications or contract documents;
b. the information provided by The Customer does not correspond to the actual situation;
c. estimated quantities deviate by more than 5%.
2. Additional work will be calculated on the basis of the price-determining factors applicable at the time the additional work is performed. The Customer is obliged topaythe to pay the price of theadditional the additional work at 2Connect's first request, without suspension or settlement (not even in the case of less work).
3. Changes to the work will only result in less work if/when:
a. 2Connect has agreed in writing not to carry out the contract reduction;
b. The contract reduction actually results in a cost saving for 2Connect and 2Connect has confirmed this to The Customer in writing;
4. Contract reductions are calculated on the basis of the amounts budgeted by 2Connect and only include savings of materials and external costs, under no circumstances savings of internal costs of 2Connect (such as staff costs).
Appears in 1 contract
Sources: Terms and Conditions