Common use of Contingency Fund Clause in Contracts

Contingency Fund. The OWNER and the PROFESSIONAL agree that certain increased cost and changes may be required because of possible omissions, ambiguities or inconsistencies in the drawings and specifications prepared by the PROFESSIONAL and, therefore, that the final construction cost of the Project may exceed the estimated construction cost. The OWNER agrees to set aside a reserve in the amount of 10 percent of the Project construction costs as a contingency to be used, as required, to pay for any such increased costs and changes. The OWNER further agrees to make no claim by way of direct or third- party action against the PROFESSIONAL or its subconsultants with respect to any increased costs within the contingency because of such changes or because of any claims made by the Contractor relating to such changes.

Appears in 3 contracts

Sources: Letter Agreement for Professional Services, Letter Agreement for Professional Services, Letter Agreement for Professional Services