Common use of Constructive changes Clause in Contracts

Constructive changes. 7.3.1 To the extent that Contractor: (i) receives a written or verbal direction or proceeding from UTA that Contractor believes to constitute a material change to the nature, character or schedule of the Work; and/or (ii) becomes aware of any circumstance or condition that expressly provides Contractor a right to a Change Order under the terms of the Contract Documents, then (in either case) Contractor shall deliver to UTA’s Project Manager written notice (hereinafter a “Potential Change Notice”) within ten (10) Days after Contractor becomes aware of (or should have reasonably become aware) the facts and circumstances which Contractor believes to give rise to a Change Order.

Appears in 2 contracts

Sources: Construction Services Agreement, Task Ordering Agreement