Construction Work and Project Schedule Clause Samples

The 'Construction Work and Project Schedule' clause defines the requirements and expectations for the timing and sequencing of construction activities within a project. It typically outlines the contractor's obligation to follow a detailed timeline, including key milestones, deadlines, and procedures for reporting progress or delays. This clause ensures that all parties are aligned on the project's timeframe, helping to coordinate resources and manage dependencies, thereby minimizing the risk of delays and disputes over scheduling.
Construction Work and Project Schedule. ‌ (a) The Initial Baseline Schedule will be the basis for monitoring the Developer’s performance of the Work until such time as a Baseline Schedule has been approved by the Department in accordance with the Technical Requirements.
Construction Work and Project Schedule. ‌ (a) The Initial Baseline Schedule will be the basis for monitoring the Developer’s performance of the Work until such time as a Baseline Schedule has been approved by the Department in accordance with the Technical Requirements. (b) The Developer and the Department will conduct monthly progress meetings in accordance with the Design-Build Contract. As part of, and in conjunction with, such meetings, the Developer will provide the Department with any proposed update of the Baseline Schedule in (c) Except as provided otherwise in this Agreement, the Developer will be financially responsible for all damage to the Project Assets resulting from the Work. The Department will not be responsible for any construction means and methods of the Developer or liability ensuing therefrom, unless such means and methods were directed by the Department pursuant to a Department Change or a Department Project Enhancement implemented by the Developer. (d) Whenever required by the Department, the Developer will provide in writing a general description of the arrangements and methods that the Developer proposes to adopt for the execution of the Work. The Developer will not significantly alter the Baseline Schedule, or such arrangements and methods, without informing the Department, and the Developer will coordinate any such alterations to take into account the Department’s resources and the work to be carried out by the Department’s separate contractors, if any. The Developer will not alter the Baseline Schedule except as permitted in the Technical Requirements. (e) If any alteration to the Baseline Schedule (i) affects the Critical Path,
Construction Work and Project Schedule. (a) The Initial Baseline Schedule will be the basis for monitoring the DB Contractor’s performance of the DB Work until such time as a Baseline Schedule has been approved by the Concessionaire (which approval shall be subject to approval by the Department in accordance with the Technical Requirements). (b) Under the CA the Concessionaire and the Department are to conduct monthly progress meetings in accordance with the Technical Requirements; the DB Contractor shall attend all such meetings unless otherwise directed by the Concessionaire. As part of, and in conjunction with, such meetings, the DB Contractor, subject to Concessionaire Approval, will provide the Department with any proposed update of the Project Schedule in accordance with the Technical Requirements. The Parties further agree to abide by the terms and procedures set forth in the Technical Requirements pertaining to project management and coordination matters. (c) Except as provided otherwise in this Agreement, the DB Contractor will be financially responsible for all damage to the Project resulting from the DB Work. Neither the Concessionaire nor the Department will be responsible for any construction means and methods of the DB Contractor or liability ensuing therefrom; provided, however, to the extent the Department incurs any liability under the CA if such means and methods were directed by the Department pursuant to a Department Change, then the DB Contractor shall not be responsible therefor to the extent liability is assumed by the Department and the Department actually pays for the costs thereof; and provided, further, that the foregoing will not limit the DB Contractor’s right to a Department Change with respect to the Existing Project Assets pursuant to Section 8.11(c) unless the Excess Rehabilitation Work is attributable to the DB Contractor’s failure to perform the DB Work in accordance with this Agreement. (d) Whenever required by the Concessionaire or, under the CA, the Department, the DB Contractor will provide in writing a general description of the arrangements and methods that the DB Contractor proposes to adopt for the execution of the DB Work. The DB Contractor will not significantly alter the Baseline Schedule, or such arrangements and methods, without Concessionaire Approval and informing the Department, on behalf of the Concessionaire, and the DB Contractor will coordinate any such alterations to take into account the Department’s resources and the work to be carried ou...
Construction Work and Project Schedule. (a) The Initial Baseline Schedule will be the basis for monitoring the Concessionaire’s performance of the Work until such time as a Baseline Schedule has been approved by the Department in accordance with the Technical Requirements. The 395 Baseline Schedule will be the basis for monitoring the Concessionaire’s performance of the Work for the 395 Project. (b) The Concessionaire and the Department will conduct monthly progress meetings in accordance with the Technical Requirements. As part of, and in conjunction with, such meetings, the Concessionaire will provide the Department with any proposed update of the Baseline Schedule in accordance with the Technical Requirements. The parties further agree to abide by the terms and procedures set forth in the Technical Requirements pertaining to project management and coordination matters. (c) Except as provided otherwise in this Agreement, the Concessionaire will be financially responsible for all damage to the Project Assets resulting from the Work. The Department will not be responsible for any construction means and methods of the Concessionaire or liability ensuing therefrom, unless such means and methods were directed by the Department pursuant to a Department Change or a Department Project Enhancement. (d) Whenever required by the Department, the Concessionaire will provide in writing a general description of the arrangements and methods that the Concessionaire proposes to adopt for the execution of the Work. The Concessionaire will not significantly alter the Baseline Schedule, or such arrangements and methods, without informing the Department, and the Concessionaire will coordinate any such alterations to take into account the Department’s 59 DMEAST #27287336 v26 resources and the work to be carried out by the Department’s separate contractors, if any. The Concessionaire will not alter the Baseline Schedule except as permitted in the Technical Requirements. (e) If any alteration (i) affects the Critical Path, (ii) adversely and materially affects the Department’s oversight resources or the Department’s separate contractors, or (iii) deviates from the Technical Requirements, the Concessionaire will not make such alteration without the prior approval of the Department. (f) If the progress of the Work does not conform to the Baseline Schedule, as updated in this Agreement, the Concessionaire will submit a recovery schedule as required by the Technical Requirements, and will reasonably consider revisions to ...
Construction Work and Project Schedule. ‌ (a) The Initial Baseline Schedule will be the basis for monitoring the Developer’s performance of the Work until such time as a Baseline Schedule has been approved by the Department in accordance with the Technical Requirements. (b) The Developer and the Department will conduct monthly progress meetings in accordance with the Design-Build Contract. As part of, and in conjunction with, such meetings, the Developer will provide the Department with any proposed update of the Baseline Schedule in accordance with the Technical Requirements. The parties further agree to abide by the terms and procedures set forth in the Technical Requirements and the Design-Build Contract pertaining to project management and coordination matters. (c) Except as provided otherwise in this Agreement, the Developer will be financially responsible for all damage to the Project Assets resulting from the Work. The Department will not be responsible for any construction means and methods of the Developer or liability ensuing therefrom, unless such means and methods were directed by the Department pursuant to a Department Change or a Department Project Enhancement implemented by the Developer. (d) Whenever required by the Department, the Developer will provide in writing a general description of the arrangements and methods that the Developer proposes to adopt for the execution of the Work. The Developer will not significantly alter the Baseline Schedule, or such arrangements and methods, without informing the Department, and the Developer will coordinate any such alterations to take into account the Department’s resources and the work to be carried out by the Department’s separate contractors, if any. The Developer will not alter the Baseline Schedule except as permitted in the Technical Requirements. (e) If any alteration to the Baseline Schedule (i) affects the Critical Path,