Construction Completion Documents Clause Samples
Construction Completion Documents. Within thirty (30) days following the completion of construction of any Improvement for which a Certificate or Temporary Certificate of Occupancy is issued; the Lessee shall furnish the following documents to the Department:
(a) Documents showing that the Improvement has met the requirements of the final inspection and that all permits have been closed out;
(b) Documents that Lessee has obtained lien waivers from the general contractor and all parties designated by the Department, along with any final affidavit of the general contractor required by Chapter 713, Florida Statutes;
(c) Certificate of Occupancy for the Improvement;
(d) Certification from the Lessee's architect that the Improvement has been completed in conformance with the approved Plans and Specification as well as all permits and applicable governmental requirements;
(e) At least one copy of an as-built survey of the area covered by the Improvement;
(f) Two (2) complete sets of as-built construction drawings and two (2) AutoCAD files of the as- built construction drawings in a compact disk format or other format designated by the Department, including all pertinent shop and working drawings and such other as-built drawings as the Department may reasonably require; and
(g) Copies of all releases of contractor claims and liens.