Construction Completion Deadline. MagneGas will complete the first Gasifier not later than 90 days from its receipt of the first Progress Payment (the “Completion Date”). To the extent that the first unit is not completed by the Completion Date, the Purchase Price will be reduced by $5,000 per completed week that transpires after the Completion Date up until the actual date on which the first unit is completed, up to a maximum reduction of $150,000.00, subject to CSE’s right to terminate this Agreement for cause in accordance with Section 7.2. If CSE terminates this Agreement due to delays in accordance with this Section 4.4, MagneGas shall promptly refund all amounts paid by CSE hereunder (except for the two non-refundable deposits referenced in Sections 4.1 and 4.2 above).