Client-Caused Changes Sample Clauses
Client-Caused Changes. In the event and to the extent (a) a failure of Client to perform, or cause performance of, its obligations in accordance with this Agreement (including any defects or deficiencies in items within Client’s Scope or interference by Client or others for whom Client is responsible) or (b) damage to or destruction of any Work caused by Client, causes a material delay in Contractor’s performance of the Work which impairs Contractor’s ability to meet the Guaranteed Completion Dates or the Project Guarantees, or materially and adversely impacts Contractor’s cost of performance of the Work, an equitable adjustment in one or more of the Guaranteed Completion Dates, the Payment Schedule, the Project Schedule, or the Contract Price and/or any other such part of this Agreement as may be affected shall be made pursuant to this Article 12. To the extent Contractor cannot reasonably redeploy labor or equipment, reasonable standby and mobilization/remobilization costs incurred by Contractor resulting from any such delay shall be reimbursed to Contractor monthly as such costs are incurred.