Claims Initiated by the Design-Builder. If the Design-Builder initiates a Claim, the Owner will take one or more of the following actions within ten days after receipt of the notice required under Section 00.0.0.0: (1) request additional supporting data, (2) render an initial decision rejecting the Claim in whole or in part, (3) render an initial decision approving the Claim, (4) suggest a compromise or (5) indicate that it is unable to render an initial decision because the Owner lacks sufficient information to evaluate the merits of the Claim.
Appears in 16 contracts
Samples: Agreement, Design Build Construction Agreement, Agreement
Claims Initiated by the Design-Builder. If the Design-Builder initiates a Claim, the Owner will take one or more of the following actions within ten 45 days after receipt of the notice required under Section 00.0.0.0: (1) request additional supporting data, (2) render an initial decision rejecting the Claim in whole or in part, (3) render an initial decision approving the Claim, (4) suggest a compromise or (5) indicate that it is unable to render an initial decision because the Owner lacks sufficient information to evaluate the merits of the Claim.
Appears in 2 contracts
Samples: sites.dfwairport.com, sites.dfwairport.com
Claims Initiated by the Design-Builder. If the Design-Builder initiates a Claim, the Owner will take one or more of the following actions within ten days after receipt of the notice required under Section 00.0.0.014.1.3: (1) request additional supporting data, (2) render an initial decision rejecting the Claim in whole or in part, (3) render an initial decision approving the Claim, (4) suggest a compromise or (5) indicate that it is unable to render an initial decision because the Owner lacks sufficient information to evaluate the merits of the Claim.
Appears in 1 contract
Samples: bchd.blob.core.windows.net
Claims Initiated by the Design-Builder. If the Design-Builder initiates a Claim, the Owner will take one or more of the following actions within ten twenty (20) days after receipt of the notice required under Section 00.0.0.0: (1) request additional supporting data, (2) render an initial decision rejecting the Claim in whole or in part, (3) render an initial decision approving the Claim, (4) suggest a compromise or (5) indicate that it is unable to render an initial decision because the Owner lacks sufficient information to evaluate the merits of the Claim.:
Appears in 1 contract
Samples: www.ci.gladstone.or.us
Claims Initiated by the Design-Builder. If the Design-Builder initiates a Claim, the Owner Manager will take one or more of the following actions within ten (10) days after receipt of the notice required under Section 00.0.0.0: (1) request additional supporting data, (2) render an initial decision rejecting the Claim in whole or in part, (3) render an initial decision approving the Claim, (4) suggest a compromise or (5) indicate that it is unable to render an initial decision because the Owner lacks sufficient information to evaluate the merits of the Claim.:
Appears in 1 contract
Samples: rfp.hawaiiconvention.com
Claims Initiated by the Design-Builder. If the Design-Builder initiates a Claim, the Owner will take one or more of the following actions within ten days after receipt of the notice required under Section 00.0.0.0: (1) request Sectio additional supporting data, (2) render an initial decision rejecting the Claim in whole or in part, (3) render an initial pa decision approving the Claim, (4) suggest a compromise or (5) indicate that it is unable to render an initial decision ren because the Owner lacks sufficient information to evaluate the merits of the Claim.
Appears in 1 contract
Samples: logoscharter.com