CIF Construction Sample Clauses
CIF Construction. The CIF shall be designed and constructed in accordance with Good Utility Practice. Within 120 Calendar Days after the Commercial Operation Date, unless the Parties agree on another mutually acceptable deadline, Customer shall deliver to Grant PUD record set drawings, information and documents for the CIF, such as: one-line and three-line
CIF Construction. The CIF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Parties agree on another mutually acceptable deadline, the Customer shall deliver “as-built” drawings, information and documents for the CIF, such as: a one-line diagram, a site plan showing the Generating Facility and the CIF, plan and elevation drawings showing the layout of the CIF, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Customer’s step-up transformers, the facilities connecting the Generating Facility to the step-up transformers and the CIF, and the impedances (determined by factory tests) for the associated step-up transformers and the Generating Facility.
CIF Construction. The CIF shall be designed and constructed in accordance with Good Utility Practice. Within 120 Calendar Days after the Commercial Operation Date, unless the Parties agree on another mutually acceptable deadline, Customer shall deliver to Grant PUD record set drawings, information and documents for the CIF, such as: one-line and three-line diagrams, a site plan showing the Generating Facility and the CIF, plan and elevation drawings showing the layout of the CIF, a relay functional diagram, relaying alternating current (AC) and direct current (DC) schematic wiring diagrams and relay settings for all facilities associated with Customer's step- up transformers, the facilities connecting the Generating Facility to the step- up transformers and the CIF, and the impedances (determined by factory tests) for the associated step-up transformers and the Generating Facility. Customer shall provide Grant PUD specifications for the excitation system, automatic voltage regulator, Generating Facility control and protection settings, transformer tap settings, and communications, if applicable.