Changes to Firm Schemes. 8.1 The parties may from time to time agree changes to the Firm Scheme Details and where such changes are agreed they shall be implemented by the Grant Recipient amending the Firm Scheme Details in IMS and the electronic confirmation of that amendment by the Agency through IMS. 8.2 Where a Milestone Failure occurs or is in the opinion of the Agency reasonably likely to occur (having regard to the information pursuant to Condition 3 or Condition 7.4) and such failure is directly caused by a Milestone Extension Event, the Agency shall, subject always to Condition 8.3, extend the relevant Milestone Date and associated Firm Scheme Completion Date by such period as it (acting reasonably) considers appropriate to take account of the delay caused or likely to be caused by the Milestone Extension Event. 8.3 The Agency shall not under any circumstances be required or obliged to extend a Firm Scheme Completion Date beyond 31 March 2018.