Common use of Budget Overruns; Program Changes Clause in Contracts

Budget Overruns; Program Changes. The Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate, then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Interests nor deemed a contribution under this Agreement. Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants in proportion to their respective Participating Interests.

Appears in 3 contracts

Samples: In Agreement (Entree Gold Inc), Equity Participation (Entree Gold Inc), In Agreement (Entree Gold Inc)

AutoNDA by SimpleDocs

Budget Overruns; Program Changes. The With respect to all adopted Programs and Budgets, the Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds an adopted Budget by more than ten fifteen percent (1015%) in the aggregate, then the excess over ten fifteen percent (1015%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 SECTION 9.13 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Interests nor deemed a contribution under this Agreement. Budget overruns of ten fifteen percent (1015%) or less in the aggregate shall be borne by the Participants in proportion to their respective Participating Interests.

Appears in 2 contracts

Samples: Agreement (Gryphon Gold Corp), Agreement (Golden Phoenix Minerals Inc /Mn/)

Budget Overruns; Program Changes. The Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If Subsequent to the Option Period, if the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate), then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager Manager, and such excess shall not be included in the calculations of the Participating Interests nor deemed a contribution under this AgreementInterests. Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants Parties, in proportion to their respective Participating InterestsInterests at the time the overrun occurs.

Appears in 2 contracts

Samples: www.sec.gov, Mining Title Township (Clifton Star Resources Inc.)

Budget Overruns; Program Changes. The Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds the total of an adopted Budget by more than ten percent (10%) in the aggregate), then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 9.6, or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Interests nor deemed a contribution under this AgreementInterests. Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants in proportion to their respective Participating InterestsInterests as of the time the overrun occurs.

Appears in 1 contract

Samples: Venture Agreement (Miranda Gold Corp)

Budget Overruns; Program Changes. The For Programs and Budgets adopted after completion of Coolcharm’s Initial Contribution, the Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate, then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Ownership Interests nor deemed a contribution under this Agreement. Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants Members in proportion to their respective Participating respec-tive Ownership Interests.

Appears in 1 contract

Samples: Operating Agreement (Western Goldfields Inc)

Budget Overruns; Program Changes. The For Programs and Budgets adopted after completion of PSI's Initial Contribution, the Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate, then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Ownership Interests nor deemed a contribution under this Agreement. Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants Members in proportion to their respective Participating Ownership Interests.

Appears in 1 contract

Samples: Joint Venture Agreement (Vista Gold Corp)

Budget Overruns; Program Changes. The Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate), then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 10.7 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Interests nor deemed a contribution under this AgreementInterests. Subject to clause 10.1 above as to Gareste, Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants in proportion to their respective Participating InterestsInterests as of the time the overrun occurs.

Appears in 1 contract

Samples: In and Joint Venture Agreement (Pan American Lithium Corp)

AutoNDA by SimpleDocs

Budget Overruns; Program Changes. The Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate, then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 9.9 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Interests nor deemed a contribution under this Agreement. Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants in proportion to their respective Participating Interests.

Appears in 1 contract

Samples: Operating Agreement (Thompson Creek Metals CO Inc.)

Budget Overruns; Program Changes. The For Programs and Budgets adopted after completion of Electrum’s Initial Contribution, the Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate, then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Ownership Interests nor deemed a contribution under this Agreement. Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants Members in proportion to their respective Participating Ownership Interests.

Appears in 1 contract

Samples: Securities Purchase Agreement (American International Ventures Inc /De/)

Budget Overruns; Program Changes. The For Programs and Budgets adopted after completion of ROYAL's Initial Contribution, the Manager shall immediately notify the Management Committee of any material departure from an adopted Program and Budget. If the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate, then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 9.13 or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager and such excess shall not be included in the calculations of the Participating Interests nor deemed a contribution under this Agreement. Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants in proportion to their respective Participating Interests.

Appears in 1 contract

Samples: Operating Agreement (Royal Gold Inc /De/)

Budget Overruns; Program Changes. The Manager shall immediately promptly notify the Management Committee of any material departure from an adopted Program and Budget. If Prior to the Stand-Alone Date, if the Manager exceeds an adopted Budget by more than ten percent (10%) in the aggregate, then the excess over ten percent (10%), unless directly caused by an emergency or unexpected expenditure made pursuant to Section 8.13 6.10 below, or unless otherwise authorized or ratified by the Management Committee, shall be for the sole account of the Manager Manager, and such excess shall not be included in as a charge against the calculations of the Participating Interests nor deemed a contribution under this AgreementBusiness Account. The Manager shall be promptly reimbursed for Budget overruns of ten percent (10%) or less in the aggregate shall be borne by the Participants Members in proportion to their respective Participating InterestsOwnership Interests at the time such overruns are incurred.

Appears in 1 contract

Samples: Contribution Agreement (Golden Phoenix Minerals Inc /Mn/)