(b)(ii). During Phase I, and at least 30 days prior to initiating Decision Point I of the Cycle, Transmission Provider will post an estimated start date for Decision Point I in order for Project developers and Eligible Customers to prepare to meet their Decision Point I requirements. Tariff, Part VII, Subpart D.3, section 309 Decision Point I
Appears in 2 contracts
Sources: Generation Interconnection Procedure, Generation Interconnection Procedures
(b)(ii). During Phase I, and at least 30 days prior to initiating Decision Point I of the Cycle, Transmission Provider will post an estimated start date for Decision Point I in order for Project developers and Eligible Customers to prepare to meet their Decision Point I requirements. Tariff, Part VIIVIII, Subpart D.3C.3, section 309 406 Decision Point I
Appears in 1 contract
Sources: Generation Interconnection Procedure