Common use of BID BREAKDOWN ON LUMP SUM Clause in Contracts

BID BREAKDOWN ON LUMP SUM. 41.1 Within fifteen (15) Days after the commencement date specified in the Notice to Proceed or Order to Work, unless otherwise directed by the Resident Engineer, the Contractor shall submit to the Resident Engineer a breakdown of its Bid price, or of lump sums bid for items of the Contract, showing the various operations to be performed under the Contract, as directed in the progress schedule required under Article 9, and the value of each of such operations, the total of such items to equal the lump sum price bid. Said breakdown must be approved in writing by the Resident Engineer.

Appears in 7 contracts

Samples: a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

AutoNDA by SimpleDocs

BID BREAKDOWN ON LUMP SUM. 41.1 74.1. Within fifteen (15) Days after the commencement date specified in the Notice to Proceed or Order to Work, unless otherwise directed by the Resident EngineerEngineer or Project Manager, the Contractor shall submit to the Resident Engineer or Project Manager a breakdown of its Bid price, or of lump sums bid for items of the Contract, showing the various operations to be performed under the Contract, as directed in the progress schedule as may be required under Article 942, and the value of each of such operations, the total of such items to equal the lump sum price bid. Said breakdown must be approved in writing by the Resident EngineerEngineer or Project Manager.

Appears in 3 contracts

Samples: Furnish and Install Agreement, a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

BID BREAKDOWN ON LUMP SUM. 41.1 41.1. Within fifteen (15) Days after the commencement date specified in the Notice to Proceed or Order to Work, unless otherwise directed by the Resident Engineer, the Contractor shall submit to the Resident Engineer a breakdown of its Bid price, or of lump sums bid for items of the Contract, showing the various operations to be performed under the Contract, as directed in the progress schedule required under Article 9, and the value of each of such operations, the total of such items to equal the lump sum price bid. Said breakdown must be approved in writing by the Resident Engineer.

Appears in 3 contracts

Samples: a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

AutoNDA by SimpleDocs

BID BREAKDOWN ON LUMP SUM. 41.1 Within fifteen (15) Days after the commencement date specified in the Notice to Proceed or Order to Work, unless otherwise directed by the Resident Engineer, the Contractor shall submit to the Resident Engineer a breakdown of its Bid bid price, or of lump sums bid for items of the Contract, showing the various operations to be performed under the Contract, as directed in the progress schedule required under Article 9, and the value of each of such operations, the total of such items to equal the lump sum price bid. Said breakdown must be approved in writing by the Resident Engineer.

Appears in 2 contracts

Samples: Construction Contract, a856-cityrecord.nyc.gov