BENCH MARKS Clause Samples

BENCH MARKS. The Contractor shall maintain any site bench marks provided by the Principal Representative and shall establish any additional benchmarks specified by the Architect/Engineer as necessary for the Contractor to layout the Work and ascertain all grades and levels as needed.
BENCH MARKS. Permanent reference bench marks established and maintained by the PSTCL are available on or close to the Project cite Contractor shall arrange to build and maintain at his cost any additional temporary bench marks that may be required by him to lay out lines levels etc., required for the completion of the work covered in the contract. The contractor shall also arrange at his cost for all necessary surveying leveling etc. to be carried out to standardize the co-ordinates and levels of these additional temporary bench marks with reference to the nearest of the permanent bench marks mentioned above. The responsibility for the accuracy of the temporary bench marks for any work carried out based on these bench marks lies entirely with the contractor.
BENCH MARKS. The Design/Build Entity shall maintain any site bench marks provided by the Principal Representative and shall establish any additional benchmarks specified by the Design Build Entity’s Architect/Engineer or Principal Representative as necessary for the Design/Build Entity to layout the Work and ascertain all grades and levels as needed.
BENCH MARKS. Permanent reference benchmarks established and maintained by the PSTCL are available on or close to the project site. Contractor shall arrange to build and maintain at his cost any additional temporary bench marks that may be required by him to lay out lines levels etc., required for the completion of the work covered in the contract. The contractor shall also arrange at his cost for all necessary surveying, leveling etc. to be carried out to standardize the co-ordinates and levels of these additional temporary bench marks with reference to the nearest of the permanent bench marks mentioned above. The responsibility for the accuracy of the temporary benchmarks for any works carried out based on these benchmarks lies entirely with the contractor.
BENCH MARKS. 4.1 Permanent Bench Marks (BM) approx. every 5KMs or permanent structures on or off the Right-of -way (ROW) shall be established and described.