BASIC CONDITIONS. In addition to the other requirements of the Construction Documents for excusable delay, a compensable delay, suspension, or interruption of the Work occurs only when the following are met: (1) The delay is caused by the breach of a fundamental obligation of the Construction Documents attributable to County; AND (2) Contractor shall provide a written notice to County within seven (7) calendar days that Contractor knows or should have known of the condition giving rise to the purported compensable delay, disruption, suspension or interruption, and said continuation affects the Contract Time as indicated by the last submitted and reasonable critical path schedule.
Appears in 3 contracts
Sources: Construction Agreement, Construction Agreement, Construction Agreement