Common use of Allow Clause in Contracts

Allow. a minimum of 10 working days for processing by the Project Manager/Architect and his consultants, as applicable. Some submittals may require more processing time based upon consultant's input and the complexity of the submittal. If certain submittals are critical, they should be so identified at time of submission. If a specific submittal cannot be reviewed and returned within 10 working days, the Architect will develop with the Project Manager and Contractor a timely "turn-around" that will not impact the construction schedule.

Appears in 2 contracts

Sources: Agreement Between Owner and Contractor, Agreement Between Owner and Contractor