After Substantial Completion. 12.2.2.1 In addition to the Contractor’s obligation under Paragraph 3.5, if, within one (1) year after the date of Substantial Completion of the Work, or designated portion thereof, or after the date for commencement of warranties established under Subparagraph 9.9.1, or by terms of an applicable special warranty required by the Contract Document, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of written notice from the Owner to do so unless the Owner has previously given the Contractor a written acceptance of such condition. This period of one (1) year shall be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual performance of the Work. This obligation under this paragraph 12.2.2 shall survive acceptance of the Work under the Contract and termination of the Contract. The Owner shall give such notice promptly after discovery of the condition. 12.2.2.2 The one (1) year period for correction of Work shall be extended with respect to 12.2.2.3 The one (1) year period for correction of Work shall not be extended by corrective Work performed by the Contractor pursuant to this Paragraph 12.2. 12.2.2.4 Upon request of Owner and prior to expiration of one (1) year from date of Substantial Completion, Engineer may conduct, and Contractor shall attend, a meeting with Owner to review facility operations and performance.
Appears in 1 contract
Sources: Construction Agreement
After Substantial Completion. 12.2.2.1 In addition to the ContractorConstruction Manager’s obligation under Paragraph Section 3.5, if, within one (1) year after the date of Substantial Completion of the Work, or designated portion thereof, or after the date for commencement of warranties established under Subparagraph Subsection 9.9.1, or by terms of an applicable special warranty required by the Contract Document, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor Construction Manager shall correct it promptly after receipt of written notice from the Owner to do so unless the Owner has previously given the Contractor Construction Manager a written acceptance of such condition. This period of one (1) year shall be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual performance of the Work. This obligation under this paragraph Section 12.2.2 shall survive acceptance of the Work under the Contract and termination of the Contract. The Owner shall give such notice promptly after discovery of the condition.
12.2.2.2 The one (1) year period for correction of Work shall be extended with respect toto portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual completion of that portion of the Work.
12.2.2.3 The one (1) year period for correction of Work shall not be extended by corrective Work performed by the Contractor Construction Manager pursuant to this Paragraph Section 12.2.
12.2.2.4 Upon request of Owner and prior to expiration of one (1) year from date of Substantial Completion, Engineer Design Professional may conduct, and Contractor Construction Manager shall attend, a meeting with Owner to review facility operations and performance.
Appears in 1 contract
After Substantial Completion. § 12.2.2.1 In addition to the Contractor’s obligation obligations under Paragraph Section 3.5, if, within one (1) year after the date of Substantial Final Completion of the Work, Work or designated portion thereof, thereof or after the date for commencement of warranties established under Subparagraph Section 9.9.1, or by terms of an applicable special warranty required by the Contract DocumentDocuments, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of written notice from the Owner to do so unless the Owner has previously given the Contractor a written acceptance of such condition. This The Owner shall give such notice promptly after discovery of the condition. If
§ 12.2.2.2 performed the Contractor fails to correct nonconforming Work within a reasonable time after receipt of notice from the Owner or Design Agent, the Owner may correct it in accordance with Section 2.4. The one-year period for correction of one (1) year Work shall be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual performance completion of that portion of the Work. This obligation under this paragraph 12.2.2 shall survive acceptance of the Work under the Contract and termination of the Contract. The Owner shall give such notice promptly after discovery of the condition.
12.2.2.2 The one (1) year period for correction of Work shall be extended with respect to
§ 12.2.2.3 The one (1) one-year period for correction of Work shall not be extended by corrective Work performed by the Contractor pursuant to this Paragraph Section 12.2.
§ 12.2.2.4 Upon request of by the Owner and prior to the expiration of one (1) year from the date of Substantial Final Completion, Engineer may conduct, the Design Agent will conduct and the Contractor shall attend, a meeting attend 2 meetings with the Owner to review the facility operations and performance.
Appears in 1 contract
Sources: Project Manual
After Substantial Completion. 12.2.2.1 In addition to the Contractor’s obligation under Paragraph 3.5, if, within one (1) year after the date of Substantial Completion of the Work, or designated portion thereof, or after the date for commencement of warranties established under Subparagraph 9.9.1, or by terms of an applicable special warranty required by the Contract Document, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of written notice from the Owner to do so unless the Owner has previously given the Contractor a written acceptance of such condition. This period of one (1) year shall be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual performance of the Work. This obligation under this paragraph 12.2.2 shall survive acceptance of the Work under the Contract and termination of the Contract. The Owner shall give such notice promptly after discovery of the condition.
12.2.2.2 The one (1) year period for correction of Work shall be extended with respect toto portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual completion of that portion of the Work.
12.2.2.3 The one (1) year period for correction of Work shall not be extended by corrective Work performed by the Contractor pursuant to this Paragraph 12.2.
12.2.2.4 Upon request of Owner and prior to expiration of one (1) year from date of Substantial Completion, Engineer may conduct, and Contractor shall attend, a meeting with Owner to review facility operations and performance.
Appears in 1 contract
Sources: Construction Contract