Additional Time for Force Majeure Sample Clauses

Additional Time for Force Majeure. If Barrick is prevented or delayed by Force Majeure from incurring Expenditures in the amounts and timeframe provided in Sections 4.10 and 5.2(a), completing a Pre-Feasibility Study as required under Section 5.2(b), or otherwise performing any of its obligations under this Agreement, Barrick shall promptly notify the Golden Entities, and if Barrick has provided such notice, then: (a) Barrick will have such additional time after the Force Majeure event ceases to exist as is equal to the duration of the Force Majeure event to incur such Expenditures, deliver such studies, and/or perform such other obligations in such amounts and times; and (b) all subsequent deadlines by which Barrick is required to perform any of its obligations under this Agreement shall also be extended by the same period of time as the duration of the Force Majeure event.