Common use of Accepted Interpretive Clause in Contracts

Accepted Interpretive. Engineering Decisions shall constitute provisions of the Technical Requirements and shall not constitute a Department Change or entitle Developer to any Extra Work Costs, Delay Costs, time or Completion Deadline extension, compensation for losses due to delays in commencement of Availability Payments or for additional interest costs due to delayed receipt of the Milestone Payment, or other relief. Subsequent Department orders and directives that are contrary to the Interpretive Engineering Decision shall constitute a Department Change.

Appears in 2 contracts

Sources: Public Private Partnership Agreement, Public Private Partnership Agreement