14B. If by the date falling twelve (12) months after the date of the first Footpath Suspension Notice or first Contractor Footpath Suspension Notice (as applicable) the Works (or the relevant part thereof) are still suspended pursuant to clause 14B.2.2 or 14B.2.3 then, unless agreed otherwise in writing between the Parties, this Agreement shall be deemed to be terminated by the Authority as at such date and notwithstanding that the Contractor or a Contractor Related Party has brought or caused to be brought on its behalf a Footpath Challenge compensation shall be paid by the Authority in accordance with the provisions of clause 42 (Compensation on Termination for Force Majeure).
Appears in 2 contracts
Sources: Project Agreement, Project Agreement