Arbitration. (a) If the Parties are unable to reach a settlement under GCC Clause 42.1 or 42.2 within twenty-eight (28) days of the first written correspondence on the matter of disagreement, then either Party may give notice to the other party of its intention to commence arbitration in accordance with GCC Sub-Clause 42.3(b);
(b) The arbitration shall be conducted in accordance with the Arbitration Act (Act No 1 of 2001) of Bangladesh as at present in force and in the place shown in the PCC. GCC 1.1(q) The Procuring Entity is: Represented by Manager (Purchase), BRTC Head Office, ▇▇, ▇▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇-▇▇▇▇. GCC 1.1(v) The site(s)/point(s) of delivery is/are: Nezarot Store, Ground Floor, BRTC Head Office, Dhaka-1000. GCC 3.1 For notices, the Procuring Entity’s contact details shall be: Attention: Manager (Purchase) Address: BRTC, Head Office, ▇▇, ▇▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇-▇▇▇▇. Telephone: ▇▇-▇▇▇▇▇▇▇▇ Electronic mail address: ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ For notices, the Supplier’s contact details shall be: Attention: Address: Telephone: Facsimile number: Electronic mail address: GCC 8.1(i) The following documents shall also be part of the Contract: Section 6. Schedule of Requirements. GCC 11 The Supplier or the Subcontractor that is a national of, or registered in, the following countries are not eligible: None. Goods and related services to be supplied shall not have their origin in the following countries: None. GCC 21.2 The packing, marking and documentation inside and outside the packages shallbe: None. GCC 22.1 The documents to be furnished by the Supplier shall be as follows: None. GCC 24.1 The original Contract price is: /-. GCC 26.1 The method and conditions of payment to be made to the Supplier under this Contract shall be as follows: (a) Advance Payment: No advanced payment shall be made. (b) On Delivery and Acceptance: As per delivery payment shall be paid pursuant to GCC Clause 21 and 22. GCC 26.3 Payments shall be made in no case later than the 30 days after submission of an invoice or request for payment by the Supplier, and after the Procuring Entity has accepted it. GCC 26.5 The rate of interest shall be the prevailing rate of interest for commercial borrowing established in the country. Not Applicable. GCC 31.1 The inspections and tests shall be: 01 year. GCC 32.3 The Warranty Period shall be: 01 year. GCC 32.7 The Supplier shall correct any defects covered by the warranty within 30 days of being notified by the Procuring Entity of the occurrence of such defects....
Arbitration. (a) If the Parties are unable to reach a settlement under GCC Clause 42.1 or 42.2 within twenty-eight (28) days of the first written correspondence on the matter of disagreement, then either Party may give notice to the other party of its intention to commence arbitration in accordance with GCC Sub-Clause 42.3(b);
(b) The arbitration shall be conducted in accordance with the Arbitration Act (Act No 1 of 2001) of Bangladesh as at present in force and in the place shown in the PCC. GCC 1.1(q) The Procuring Entity is: Represented by Manager (Purchase), BRTC Head Office, ▇▇, ▇▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇-▇▇▇▇..▇▇ GCC 1.1(v) The site(s)/point(s) of delivery is/are: BRTC All Bus & Truck Depots: (Motijheel Bus Depot, Joarsahara Bus Depot, Mirpur Bus Depot, Mohammadpur Bus Depot, Kollayanpur Bus Depot, Jatrabari Bus Depot, Gabtoli, Gazipur Bus Depot, Mymensing Bus Depot, Narayangonj Bus Depot, Narsingdi Bus Depot, Cumilla Bus Depot, Sonapur Bus Depot, Sylhet Bus Depot, Chittagong Bus Depot, Barisal Bus Depot, Khulna Bus Depot, Rangpur Bus Depot, Bogura Bus Depot, Pabna Bus Depot, Dinajpur Bus Depot & Dhaka Truck Depot, Chittagong Truck Depot). GCC 3.1 For notices, the Procuring Entity’s contact details shall be: Attention: Manager (Purchase) Address: BRTC, Head Office, ▇▇, ▇▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇-▇▇▇▇. Telephone: ▇▇-▇▇▇▇▇▇▇▇ Electronic mail address: ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ For notices, the Supplier’s contact details shall be: Attention: Address: Telephone: Facsimile number: Electronic mail address: GCC 8.1(i) The following documents shall also be part of the Contract: Section 6. Schedule of Requirements. GCC 11 The Supplier or the Subcontractor that is a national of, or registered in, the following countries are not eligible: None. Goods and related services to be supplied shall not have their origin in the following countries: None. GCC 21.2 The packing, marking and documentation inside and outside the packages shallbe: None. GCC 22.1 The documents to be furnished by the Supplier shall be as follows: None. GCC 24.1 The original Contract price is: Tyre /-. GCC 26.1 The method and conditions of payment to be made to the Supplier under this Contract shall be as follows: (a) Advance Payment: No advanced payment shall be made. (b) On Delivery and Acceptance: As per delivery payment shall be paid pursuant to GCC Clause 21 and 22. GCC 26.3 Payments shall be made in no case later than the 30 days after submission of an invoice or request for payment by the Supplier, and after the Procu...
Arbitration. (a) If the Parties are unable to reach a settlement under GCC Clause 18.1 within twenty eight (28) days of the first written correspondence on the matter of disagreement, then either Party may give notice to the other party of its intention to commence arbitration in accordance with GCC Sub Clause 18.2 (b);
(b) The arbitration shall be conducted in accordance with the Arbitration Act (Act No 1 of 2001) of Bangladesh as at present in force and in the place shown in the PCC. GCC 1.1 (i) The Procuring Entity is Attention: Manager (Purchase), BRTC Head Office. Address: ▇▇▇▇, ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇ ▇▇▇▇▇, ▇▇ ▇▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇-▇▇▇▇. GCC 5.1 The documents to be furnished by the Supplier shall be as follows: a. Supplier’s invoice /Chalan showing Goods’ description, quantity, unit rates, total amount etc; b. Supplier’s Warranty Certificate (if any); GCC 8.1 The Contract price is Tk. Will be inserted in NOA GCC 13.1 The Warranty Period shall be : 01 (One) year. GCC 15.1 The amount of Liquidated Damages is 0.1 of ONE (1) percent of the contract value of the undelivered Goods or any part thereof delivered after expiry of the Delivery and Completion Schedule or extended Delivery and Completion Schedule, as applicable, per day of delay. Guide to application of GCC Sub Clause 15.1 above [ Liquidated damages is equivalent to an amount to be determined in accordance with the following formulae T = V x Px n Where; T = Total amount of Liquidated Damages V = Contract Value of undelivered Goods or any part thereof, delivered after expiry of the Delivery and Completion Schedule or extended Delivery and Completion Schedule, as applicable P = Percent-rate at which the Liquidated Damages shall be imposed per day of delay n = No of days delayed for delivery of the undelivered Goods or any part thereof, after expiry of the Delivery and Completion Schedule or extended Delivery and Completion Schedule, as applicable. The maximum amount of Liquidated Damages for the undelivered Goods or any part thereof is 10% percent of the final Contract Price of the whole of the Goods and related services. GCC 18.2(b) Arbitration shall take place in: Chairman, BRTC, Head Office, ▇▇▇ ▇▇▇▇▇, ▇▇ ▇▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇-▇▇▇▇. BR – 3 Specifications Submission and Compliance Sheet Forms BR-1 to BR-3 comprises part of the Tender. Forms BR-4 to BR-5 comprises part of the Contract. Invitation for Tender No: 35.04.0000.017.00.573.22 Tender Package No: Single Lot No: Single Date : Taka [insert amount] [ in figures] Ta...