Weekly Status Reports Sample Clauses

Weekly Status Reports. The Settlement Administrator shall provide a weekly status report to the Parties. As part of its weekly status report, the Settlement Administrator will inform Class Counsel and Defendants’ Counsel of the number of Notices mailed, the number of Notices returned as undeliverable, the number of Notices re-mailed, and the number of requests for exclusion or objections received.
AutoNDA by SimpleDocs
Weekly Status Reports. The Contractor shall prepare and deliver a Weekly Status Report for all work performed under the contract by task order. The report shall include the technical progress and status of work at the task order level. The report shall be provided on a weekly basis on a standard day/time to be determined after the contract kick-off but will be required one (1) day prior to the weekly status call. At some point, the weekly status report may be divided into separate weekly reports by task order if the one report becomes too large. The technical progress report shall include at a minimum: • A narrative review of work accomplishments and/or significant events for the previous week. • Indicate outstanding and completed deliverables and work products, risks, staffing status and project schedules. • Document any technical performance problems or challenges and the steps being taken to correct them.
Weekly Status Reports. Prime contractor shall produce a weekly status report that includes at a minimum the following;
Weekly Status Reports. During construction, the Certificate Holder will provide DPS Staff and the NYSDEC (and NYSDOT when state highways are affected) with weekly status reports. These reports will summarize construction activities and indicate construction activities and locations scheduled for the following twoweeks.
Weekly Status Reports. A weekly status report is submitted by the Contractor to the Project Manager. This report is less formal than the monthly report and is used as a tool for the day-to-day management of the project. Contents of a weekly report will include the following items:  The updated Primavera programme or MS Project  Programme summary narrative  Progress and performance summaries  Sectional Completion and Key Milestone status
Weekly Status Reports. EMACHINES shall provide ODM and TGA with accurate records of RA on a [*] basis.
Weekly Status Reports. To Agent, on or prior to 9:00 a.m. (New York time) on each Monday following the first Monday after the Closing Date, a detailed status report setting forth the Borrower’s efforts to refinance in full in cash the Obligations and sell the Montvale Property, and such other information as may be reasonably requested by Agent, in each case in form and substance reasonably satisfactory to Agent. (q)
AutoNDA by SimpleDocs
Weekly Status Reports. ALLTEL will prepare a weekly status report for Client's Project Manager describing work completed, work in progress, and any critical issues pertaining to the deployment project's completion.
Weekly Status Reports a. The Audiovisual Integrator shall provide weekly progress updates to the Ar- chitect and Audiovisual Consultant. Weekly Status Reports shall be submit- xxx as directed by the CM via faxed hard copy or electronic means (i.e. email). Issuance of Weekly Status Reports shall commence from the date of the first submittal delivery and shall continue until contract closeout.
Weekly Status Reports. Weekly written status reports shall be provided by Vendor to the TEC Contracting Entity for any source code changes or modifications affecting the TEC Contracting Entity that require 40 or more hours to complete. Unless otherwise mutually agreed to by the TEC Contracting Entity and Vendor, weekly status reports shall be provided no later than 4:00 p.m. each Friday. Weekly status reports shall include, but are not limited to the following:
Time is Money Join Law Insider Premium to draft better contracts faster.