Stop Work Order Sample Clauses

Stop Work Order. (a) NYSERDA may at any time, by written Order to the Contractor, require the Contractor to stop all or any part of the Work called for by this Agreement for a period of up to ninety (90) days after the Stop Work Order is delivered to the Contractor, and for any further period to which the parties may agree. Any such order shall be specifically identified as a Stop Work Order issued pursuant to this Section. Upon receipt of such an Order, the Contractor shall forthwith comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Order during the period of work stoppage consistent with public health and safety. Within a period of ninety (90) days after a Stop Work Order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, NYSERDA shall either:
AutoNDA by SimpleDocs
Stop Work Order. 8.2.1. The State may, at any time, by written order to the Contractor, require the Contractor to stop all or any part, of the work called for by this Contract for period(s) of days indicated by the State after the order is delivered to the Contractor. The order shall be specifically identified as a stop work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage.
Stop Work Order. The State may suspend any or all activities under the Contract at any time. The State will provide Contractor a written stop work order detailing the suspension. Contractor must comply with the stop work order upon receipt. Within 90 calendar days, or any longer period agreed to by Contractor, the State will either: (a) issue a notice authorizing Contractor to resume work, or (b) terminate the Contract or delivery order. The State will not pay for Contract Activities, Contractor’s lost profits, or any additional compensation during a stop work period.
Stop Work Order. State may, at any time, by written order to Contractor require Contractor to stop any or all parts of the work required by this Contract for the period of days indicated by State after the order is delivered to Contractor. The order must be specifically identified as a stop work order issued under this clause. Upon receipt of the order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. If a stop work order issued under this clause is canceled or the period of the order or any extension expires, Contractor shall resume work. The State Project Manager shall make the necessary adjustment in the delivery schedule or contract price, or both, and this Contract shall be amended in writing accordingly.
Stop Work Order. The Buyer may, at any time, by written order to the Seller, require the Seller to stop all or any part of the work called for by this Order (“Stop-Work Order”) for a period of up to 180 days after the Stop-Work Order is delivered to the Seller, and for any further period to which the parties may agree. The Stop-Work Order shall be specifically identified as such issued under this Section. Upon receipt of the Stop-Work Order, the Seller shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by this Order during the period of work stoppage. At the expiration of the Stop Work Order period, or within any extension of that period to which the parties shall have agreed, the Buyer shall either (a) cancel the Stop-Work Order, or (b) terminate the work covered by the Stop-Work Order.
Stop Work Order. The Department may suspend any or all activities under this Agreement at any time. The Department will provide the Grantee with a written stop order detailing the suspension. Grantee must comply with the stop work order upon receipt. The Department will not pay for Activities, Grantee’s lost profits, or any additional compensation during a stop work period.
Stop Work Order. (A) Order to Stop Work. The COMMISSION may, by written order to the CONTRACTOR at any time, and without notice to any surety, require the CONTRACTOR to stop all or any part of the work called for by this CONTRACT. This order shall be for a specified period not exceeding twenty-four (24) months after the order is delivered to the CONTRACTOR unless the parties agree to any further period. Any such order shall be identified specifically as a stop work order issued pursuant to this clause. Upon receipt of such an order, the CONTRACTOR shall forthwith comply with its terms and take all steps to minimize the occurrence of costs allocable to the work covered by the order during the period of work stoppage. Before the stop work order expires, or within any further period to which the parties shall have agreed, the COMMISSION shall either:
AutoNDA by SimpleDocs
Stop Work Order. (a) Seller shall stop Work for up to ninety (90) days in accordance with the terms of any written notice received from Buyer, or for such longer period of time as the Parties may agree and shall take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by this Contract during the period of Work stoppage.
Stop Work Order. Xxxxxxx County may, by issuing a Stop Work Order, require that the Contractor fully or partially stop work for a period of up to 90 calendar days, and for any further period to which the parties agree. Upon receipt of the Stop Work Order, the Contractor must immediately take all reasonable steps to minimize incurring costs. Within the period of the Stop Work Order, Xxxxxxx County must either: (a) terminate the Stop Work Order; or
Stop Work Order. DSA may issue a Stop Work Order, or an Order to Comply, when either