Owner’s Right to Suspend Work Sample Clauses

The Owner’s Right to Suspend Work clause grants the project owner the authority to temporarily halt construction or related activities at their discretion. In practice, this clause outlines the procedures the owner must follow to notify the contractor of a suspension, the contractor’s obligations during the suspension period, and any adjustments to the project schedule or compensation that may result. Its core function is to provide the owner with flexibility to address unforeseen circumstances or changes in project requirements while establishing a clear process to minimize disputes and protect both parties’ interests.
POPULAR SAMPLE Copied 8 times
Owner’s Right to Suspend Work. The Owner reserves the right, with or without the concurrence of the Design
Owner’s Right to Suspend Work. The Owner reserves the right, with or without the concurrence of the Design Professional, to suspend the Work at any time or from time to time at the Owner's sole discretion, upon giving Contractor five days advanced written notice thereof. If the Owner exercises this right and then resumes the Work covered hereby, Contractor shall be entitled upon timely claim to a Change Order for payment by Owner of any reasonable Actual Costs actually incurred by Contractor in connection with the suspension and resumption of the Work, as well as an extension in the time for performance of the Work to the extent Contractor is delayed The Design Professional shall determine the time, which shall be binding upon both Owner and Contractor, as set forth in Section 3, Part 3.
Owner’s Right to Suspend Work. The Owner reserves the right, with or without the concurrence of the Design Professional, to suspend the Work at any time or from time to time at the Owner's sole discretion, upon giving Contractor five days advanced written notice thereof. If the Owner exercises this right and then resumes the Work covered hereby, Contractor shall be entitled upon timely claim to a Change Order for payment by Owner of any reasonable Actual Costs actually incurred by Contractor in connection with the suspension and resumption of the Work, as well as an extension in the time for performance of the Work to the extent Contractor is delayed by Owner's suspension, to include compensation based upon the rate for Time Dependent Overhead Costs. The Design Professional shall determine the time, which shall be binding upon both Owner and Contractor, as set forth in Section 3, Part 3.
Owner’s Right to Suspend Work. Owner may, with or without cause and in its sole discretion, order Contractor in writing to suspend, delay or interrupt the Work in whole or in part for a period not to exceed fifteen (15) days. Nothing in this provision shall give Contractor any right to a termination or to an adjustment in Contract Sum, provided that the Construction Schedule shall be equitably adjusted.
Owner’s Right to Suspend Work. The Owner reserves the right, with or without the concurrence of the Program Manager or Program Manager, to suspend the work at any time or from time to time at the Owner's sole discretion, upon giving Design-Builder five (5) days advanced written notice thereof. If the Owner exercises this right and then resumes the work covered hereby, Design-Builder shall be entitled, upon timely claim to a Change Order, to payment by Owner of any reasonable Actual Costs incurred by Design-Builder in connection with the suspension and resumption of the work, as well as to an extension in the time for performance of the work to the extent Design-Builder is delayed by Owner's suspension.
Owner’s Right to Suspend Work. The Owner may at any time suspend the Work or any part thereof, immediately and verbally for reasons of safety, or by giving reasonable notice to the Contractor in writing. The Work shall be resumed by the Contractor within ten (10) days after the date fixed in the written notice from the Owner to the Contractor to do so. The Owner shall reimburse the Contractor for reasonable expenses directly incurred by the Contractor in connection with the Work under this Agreement as a result of such suspension. When the whole or any portion of the Work is suspended for any reason, the Contractor shall properly cover, secure, and protect or cause to be so protected, such Work as may be liable to sustain injury from any cause.
Owner’s Right to Suspend Work. The Owner reserves the right, with or without the concurrence of the Design Professional or Program Manager, to suspend the work at any time or from time to time at the Owner's sole discretion, upon giving CM/GC five (5) days advanced written notice thereof. If the Owner exercises this right and then resumes the work covered hereby, CM/GC shall be entitled, upon timely claim to a Change Order, to payment by Owner of any reasonable Actual Costs incurred by CM/GC in connection with the suspension and resumption of the work, as well as to an extension in the time for performance of the work to the extent CM/GC is delayed by Owner's suspension. Owner’s and Program Manager’s Right to Stop Work. The Owner reserves the right, for itself and the Program Manager, and for any retained Owner’s Construction Inspector, upon observation of apparent nonconforming work, to immediately stop the affected work at any time by oral direction at the Owner's or Program Manager’s sole discretion, with notice to be provided to CM/GC within 72 hours. If the work is later determined by the Design Professional to be in fact conforming work, then CM/GC, for the period commencing 72 hours after the issuance of the initial stop work order, shall be entitled, upon timely claim to a Change Order, to payment by Owner of any reasonable Actual Costs incurred by CM/GC in connection with the stop work order and resumption of the work, as well as to a non-compensable extension in the time for performance of the work to the extent CM/GC is delayed by Owner's stop-work order beyond the initial 72 hours.
Owner’s Right to Suspend Work. The Owner may at any time issue a Change Order to the Vendor to suspend all or any part of the Work for such period of time as the Owner may reasonably determine to be appropriate. Any such Change Order shall be handled in accordance with the provisions of Section 11 hereof.
Owner’s Right to Suspend Work. The Owner may, at any time and upon reasonable notice to the Vendor, order the Vendor, in writing, to suspend all or any part of the Work for such reasonable period of time as the Owner may reasonably determine to be appropriate for its convenience. Any request by the Vendor for a change in the Specifications caused by the Owner's suspension of the Work pursuant to this subsection 25.1 will be subject to the review and reasonable acceptance of the Owner. No modification to the Specifications will be made to the extent that performance is, was or would have been suspended, delayed or interrupted for any other cause due to the Vendor's fault or if the suspension had no effect on agreed upon performance deadlines and/or Project Milestones set forth in this Contract. In the event of any such suspension, the Vendor will be compensated for any actual and reasonable loss, actual and reasonable damages or actual and reasonable expenses arising directly from such delay, including but not limited to payments contractually required under any Subcontractor agreements and reimbursement of reasonable expenses associated with the necessary re-deployment of the Vendor's resources; provided that the Vendor will in such event use reasonable efforts to estimate and report to the Owner any such costs or expenses prior to the commencement of any such Owner suspension pursuant to this subsection 25.1.
Owner’s Right to Suspend Work. The Owner reserves the right, with or without the concurrence of the Design Professional or Program Manager, to suspend the work at any time or from time to time at the Owner's sole discretion, upon giving CM/GC five (5) days advanced written notice thereof. If the Owner exercises this right and then resumes the work covered hereby, CM/GC shall be entitled, upon timely claim to a Change Order, to payment by Owner of any reasonable Actual Costs incurred by CM/GC in connection with the suspension and resumption of the work, as well as to an extension in the time for performance of the work to the extent CM/GC is delayed by Owner's suspension.