Master Project Schedule Sample Clauses

Master Project Schedule. Prior to the submittal of its first application for payment, the Construction Manager shall submit to the Owner and Design Professional for their review and approval a Master Project Schedule covering the planning and design approvals, construction, and Owner occupancy of the Project. This schedule shall conform to the format outlined in Section 3.4
AutoNDA by SimpleDocs
Master Project Schedule. Prior to the submittal of its first application for payment, Construction Contractor shall submit to Owner and Design Professional for their review and approval a Master Project Schedule covering the planning and design approvals, construction, and Owner occupancy of the Project. This schedule shall conform to the format outlined in Subsection 3.4 below. Further, this schedule shall account for any Owner scheduling requirements, such as prohibiting any Work in or near any areas where standardized assessment testing or other assessment testing is taking place during such testing that would disturb or interfere with such testing. This schedule shall serve as the framework for the subsequent development of all detailed schedules and shall be updated monthly by Construction Contractor throughout the Project. Within fifteen (15) calendar days of Construction Contractor’s submittal, Owner and Design Professional shall review the schedule and provide Construction Contractor a written list of corrections needed to approve the schedule. Construction Contractor must make all corrections and resolve all comments within thirty (30) calendar days after its receipt of Owner’s and Design Professional’s comments. If the schedule is not approved within said thirty (30) calendar days, Owner may withhold all Contract payments until the schedule is approved. The acceptance of the schedule by Owner and Design Professional in no way attests to the validity of the assumptions, logic constraints, dependency relationships, resource allocations, manpower and equipment, and any other aspect of the proposed schedule. Construction Contractor is and shall remain solely responsible for the planning and execution of all Work in order to meet Project milestones or Contract completion dates.
Master Project Schedule. Upon award of this Agreement, the Construction Team, shall submit a master project schedule covering the planning and design approvals, construction and Owner occupancy of the Project. This schedule will serve as the framework for the subsequent development of all detailed schedules. The master project schedule shall be produced and updated monthly throughout the project.
Master Project Schedule. The Construction Manager shall develop a Master Project Schedule for the Project, subject to approval by the District, which shall contain key milestones to be accomplished by the participants, including milestone completion dates for the Architect’s and any consultant’s design activities. The Master Project Schedule shall be consistent with the schedule attached hereto as Exhibit “A” and incorporated herein. The Master Project Schedule shall contain a critical path schedule for the construction of the Project and shall provide all major elements including dates, durations, phasing, milestones, and general sequencing necessary for the completion of the Project. The Master Project Schedule shall utilize the completion date of , 20 . The Construction Manager shall periodically update the Master Project Schedule for the Project and submit each update to the District for the District’s approval. Based on the approved Master Project Schedule, the Construction Manager shall prepare an Outline Schedule that includes all requirements of the Project. The Outline Schedule will be issued to all bidders for the Project and will be used by the Trade Contractors to prepare their Trade Contractor Baseline Schedules and to prepare the Project Baseline Schedule.
Master Project Schedule. The Construction Manager shall develop a Master Project Schedule for the Project, subject to approval by District, which shall contain key milestones to be accomplished by the participants, including milestone completion dates for the Architect’s and any consultant’s design activities. The Master Project Schedule shall be consistent with the schedule attached hereto as Exhibit “A” and incorporated herein. The Master Project Schedule shall contain a critical path Master Construction Schedule for the Project and shall provide all major elements. The Master Project Schedule shall utilize the completion date of ________________________, 20__. If necessary, the Construction Manager shall periodically update the Master Project Schedule for the Project and submit each update to the District for the District’s approval.
Master Project Schedule. Within fourteen (14) calendar days after the starting date on the Notice to Proceed, the CMR shall prepare and submit to the Judicial Council for review and acceptance, with copy to the Architect, a detailed, fully cost-loaded, draft Master Project Schedule. This schedule, once accepted by the Judicial Council, will be the Master Project Schedule and must be a fully cost- loaded schedule, as defined herein and shall be used for determining progress payments.
Master Project Schedule. The CMR’s Cost Loaded, Master Project Schedule shall not provide a schedule that has a later Completion date for the Construction Phase than indicated herein, unless approved in writing by the Judicial Council.
AutoNDA by SimpleDocs
Master Project Schedule. Following the Work Breakdown Structure, this schedule identifies the activities, key milestones, and estimated duration for activities on the project. It shall also highlight all agreed activities, deliverables, or milestones; for which Sheriff’s and Probation Departments are responsible, that will affect the success of the project. All project activities, deliverables, and milestones (Contractor, Sheriff’s Department and Probation Department) will be linked into a Critical Path Analysis. The Contractor, Sheriff’s Department, and Probation Department will review this analysis on a monthly basis.
Master Project Schedule. The term “Master Project Schedule” shall mean the overall schedule for completion of Project as prepared by the City and included in the RFP.
Master Project Schedule. The Construction Manager shall develop a Master Project Schedule for the Project, subject to approval by District, which shall contain key milestones to be accomplished by the participants, including milestone completion dates for the Architect’s and any consultant’s design activities. The Master Project Schedule shall be consistent with theCM Services Project Schedule, Exhibit C” and attached hereto as “Exhibit C” and incorporated herein. The Master Project Schedule shall contain a critical path Master Construction Schedule for the Project and shall provide all major elements. The Master Project Schedule shall endeavor to utilize the completion date as identified in “Exhibit C.” If necessary, the Construction Manager shall periodically update the Master Project Schedule for the Project and submit each update to the District for the District’s approval.