Final Completion Report Sample Clauses

Final Completion Report. As soon as possible after the Project Completion Date, but in no event later than the Grant Closing Date, unless IFAD has agreed in writing to an extension, the Recipient shall submit to IFAD a Final Completion Report in satisfactory form, including both technical and financial information, i.e. the project completion report, the final certified SOE and the related Audit Opinion, following the formats provided at xxx.xxxx.xxx/xxxxxxxxxx.
AutoNDA by SimpleDocs
Final Completion Report. Upon completion of all Recreational Improvements required under Section 6.1, Lessee shall, within a reasonable time thereafter, furnish City, at no charge, a certificate certifying that the Recreational Improvements have been constructed in accordance with the approved plans and specifications and in compliance with all applicable laws, and that all costs and expenses for the Recreational Improvements on the Premises have been paid or provision has been made for payment (or otherwise subject to dispute resolution process regarding such payment).
Final Completion Report. The Development Manager shall prepare and distribute to the Management Committee and each Participant a final completion report within a commercially reasonable period of time following termination of this Agreement, which shall include a complete cost report for Development Work.
Final Completion Report. If CCGJ and the City determine that the Artwork and the installation thereof is completed in accordance with this Agreement and Section 2.4.5.3, CCGJ will prepare a “Final Completion Report” to be executed by Artist and CCGJ and the City. The Final Completion Report shall include, at a minimum, the location and detailed description of the Artwork and any additional information as determined by CCGJ. The execution of the Final Completion Report by both parties shall constitute Final Acceptance.
Final Completion Report. A complete summary of Construction Costs, a description of the Transmission System, and a summary of each Participant's contributions to Construction Costs.
Final Completion Report. The Consultants will prepare a comprehensive final completion report once the Project reaches the stage of substantial completion. The report must be submitted immediately after the “Taking Over” of the completed works and shall include the key information, but not limited to the following:-
Final Completion Report. Within thirty (30) days after Final Completion of the Project, the Project Developer shall deliver or cause to be delivered to the CCR a report which shall set forth: (i) the total Project Costs incurred in connection with the design, construction, furnishing and equipping of the Project Improvements through the date of such report, (ii) all warranty items which are in the process of, or will be, corrected and the schedule for such corrections, and (iii) the status of any Actions affecting the Project Developer or the City and related to the Project. After delivery of the aforesaid report, the Project Developer shall continue to deliver, or cause to be delivered, to the CCR, an updated monthly completion report until (x) no Project Costs are sought for payment from the Project Development Fund, (y) all warranty items are corrected, and (z) no Actions remain against either or both Parties arising out of or pertaining to this Agreement.
AutoNDA by SimpleDocs
Final Completion Report. If the Contract Administrator determines that the Artwork is complete, Contract Administrator will prepare a final completion report (the “Final Completion Report”) to be executed by both Parties. The Final Completion Report shall include, at a minimum, the location, a detailed description, and the value of the Artwork (including the Artist’s basis for the determination of value) and any information requested by County per Exhibit C (Cataloguing Form), and shall refer the Artwork to the Committee and the Council to authorize final payment upon completion of all Artist’s obligations under the Agreement [DELETE IF NOT APPLICABLE]. Contract Administrator will send the Final Completion Report to County’s Risk Management Division to enable that County to insure the Artwork.
Final Completion Report. A ·complete summary of Construction Costs, a description of ANPP and a summary of each Participant's contributions to Construction Costs.
Final Completion Report. Within ninety (90) days after Final Completion of the Project, Developer shall deliver, or cause to be delivered, to the County a report that shall set forth: (a) the total Project Costs incurred in connection with the design, construction, furnishing and equipping of the Facility through the date of such report, (b) all warranty items that are in the process of, or will be, corrected and the schedule for such corrections, and (c) the status of any Actions affecting Developer or the County and related to the Project. After delivery of such report, Developer shall continue to deliver, or cause to be delivered, to the County, an updated monthly final completion report until (i) no Project Costs are sought for payment from the Construction Trust Fund, (ii) all warranty items are corrected, and (iii) no Actions remain against either or both Parties arising out of or pertaining to this Agreement.