Early Work Sample Clauses

Early Work. Early Work shall mean Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of the GMP. Permissible Early Work shall be limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the Project for which performance prior to establishment of the GMP will materially affect the critical path schedule of the Project.
AutoNDA by SimpleDocs
Early Work. Design-Builder and Owner may enter into one or more Early Work Amendment identifying specific Work that shall be performed prior to a Pricing Amendment that includes such Work, subject to a not-to-exceed budget and price. All Early Work shall be performed and Owner shall pay for the same in accordance with the terms of the Contract Documents and the terms of the applicable Early Work Amendment.
Early Work. Construction Manager and Owner may enter into one or more Early Work Amendments identifying specific Work that shall be performed prior to the Project’s first GMP Amendment and subject to a not-to-exceed budget and price for the relevant Cost of the Work stated in such Early Work Amendment. Construction Manager shall be paid the Cost of the Work for all executed Early Work plus Construction Manager’s Fee for such Work. All Early Work shall be performed and Owner shall pay for the same in accordance with the terms of the Contract Documents and the terms of the applicable Early Work Amendment.‌ Prior to commencing any Early Work: (i) Design Professional shall have issued Construction Drawings and Specifications for that Early Work; (ii) Governmental Approvals necessary to commence such Early Work shall have been issued; (iii) Construction Manager shall have submitted, for Owner Partiesreview and approval, a Construction Schedule and cost estimate for the Early Work; (iv) Construction Manager shall have selected Subcontractors to perform the Early Work in accordance with Section 6.4; and (v) Owner Parties shall have issued a Notice to Proceed with the Early Work. The Cost of the Work for all Early Work shall be included in the GMP of the applicable GMP Amendment and Construction Manager’s obligation to develop its GMP Amendments shall not be deferred or waived by any Early Work Amendment.
Early Work. That portion of the Work that the Port and GC/CM agree to perform prior to the execution of the MACC Amendment, as reflected in an Early Work Amendment.
Early Work. City may at any time require City to provide a proposal for performance of Early Work identified by City and may issue a Change Order or Directive Letter for performance of such Work, even though Construction Phase Approval has not yet been provided. In such case:
Early Work. Developer agrees that with respect to any Early Work consisting of site work, utility work, environmental remediation or ancillary demolition, (a) any such work must be consistent with the Project Concept Plan and Mandatory Project Elements and must be performed in accordance with the requirements of the City Code and any other applicable laws, (b) Developer shall have obtained, and shall have delivered to City a copy of, all Governmental Approvals necessary for the commencement and performance of such work, (c) Developer shall have entered into, and delivered to the City a duly executed copy of, the construction contract or construction contracts between Developer and duly licensed general contractor(s) for such work, (d) Developer shall have presented evidence reasonably acceptable to the City that all insurance coverages required under this Agreement are in place and (e) Developer shall have executed a site access agreement with the Marina Lessee and/or Existing Marina Lessee permitting access to the portions of the Development Site leased to the Marina Lessee and/or Existing Marina Lessee as necessary.
Early Work. Early Work shall mean Construction Services authorized by Pre-GMP Amendment that the parties agree should be performed in advance of establishment of the entire GMP for the Work. Permissible Early Work shall be limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance Work related to critical components of the Project for which performance prior to establishment of the GMP will materially and positively affect the development of the completion of the Project. The City will only compensate the CM/GC for Early Work if it is authorized in an Early Work Amendment.
AutoNDA by SimpleDocs
Early Work. If an employee is scheduled to report prior to the regular starting time of his/her shift, it is understood that employee will not be paid on a daily overtime basis for his/her hours worked prior to his/her regular starting time.
Early Work. In 1986 [00] Xxxxxx studied a one-dimensional RW that is a deterministic functional of a randomly fluctuating environment, which can be considered as a degenerate case of a RW in a dynamic RE. The model is defined as follows. For each x ∈ Z, let ξ = (ξt(x))t≥0 be an independent stationary continuous-time Markov process with state space {+1, −1} and transition probability matrix ,
Early Work. In accordance with Article 3.2 of the CM/GC Contract, which authorizes the CM/GC to perform Construction Phase Services in advance of the execution of a GMP Amendment if an Early Work Amendment is executed, Owner and the CM/GC hereby agree that the CM/GC shall perform the Early Work generally described below and more specifically described in the Documents for the Early Work that are listed in Exhibit D.A to this Amendment, including any Early Work Plans and Specifications. Exhibit D.A and all Documents listed in Exhibit D.A are by this reference incorporated herein. The CM/GC will provide all labor, materials, supervision, coordination, and equipment necessary to complete the following Early Work: . Work will take place on as indicated in the drawings noted in Exhibit D.A. Upon completion of and review by Owner and Architect, the CM/GC will provide _. The CM/GC shall not be authorized or required to execute any other Work under the CM/GC Contract by virtue of this Amendment. Owner does not, by execution of this Amendment, bind itself to specific rates for use in future amendments, including hourly rates charged for CM/GC’s project management personnel or stated rental rates, but reserves the right for future negotiation of those rates.