CONTRACTOR’S CONSTRUCTION SCHEDULES Clause Samples
The "Contractor’s Construction Schedules" clause defines the contractor’s obligation to prepare, maintain, and update detailed timelines for the execution of construction work. Typically, this clause requires the contractor to submit an initial schedule for approval, regularly update it to reflect progress or delays, and coordinate with the project owner or architect regarding any changes. Its core practical function is to ensure that all parties have a clear, up-to-date understanding of project timelines, which helps manage expectations, track progress, and address potential delays proactively.
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The contractor shall furnish, not later than fifteen (15) days after receipt of "Notice-to-Proceed", a CPM schedule showing the expected times of completion of the various stages of work on this project. The schedule shall be a C.P.M. (Critical Path Method) chart. The work headings therein shall correspond generally with the headings listed in the Contractor's Schedule of Values. Refer to Division 1 - General Requirements. Final times of completion in the schedule shall not exceed the completion date required by the contract Documents. During progress of the work the Contractor shall enter on the schedule that Actual progress at the end of each month, and shall deliver two (2) copies to the Architect along with the Contractor's pay request. Contractor's pay request will not be processed until receipt and review of monthly updated CPM Chart. The schedule shall be cost loaded and be considered in submitting and approving, all progress payments.
3.10.2 The Contractor shall prepare as provided herein and keep current, for the Architect’s approval, a schedule of submittals which is coordinated with the Contractor’s construction schedule and allows the Architect reasonable time to review submittals. The schedule shall be drawn to a time scale and shall indicate the date of commencement and completion of each work item. At a minimum, the schedule shall indicate individual work items for each applicable section of the Specifications, further subdivided as necessary to indicate sitework and each building in the Project. The items shown shall be directly related to the items listed in the approved Schedule of Values required in Paragraph 9.
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner’s and Architect’s information a Contractor’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
§ 3.10.2 The Contractor shall prepare a submittal schedule, promptly after being awarded the Contract and thereafter as necessary to maintain a current submittal schedule, and shall submit the schedule(s) for the Architect’s approval. The Architect’s approval shall not unreasonably be delayed or withheld. The submittal schedule shall (1) be coordinated with the Contractor’s construction schedule, and (2) allow the Architect reasonable time to review submittals. If the Contractor fails to submit a submittal schedule, the Contractor shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals.
§ 3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect.
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 9.8.1 The Contractor, promptly after being awarded the Contract, shall submit for the Owner’s and Architect’s information a Contractor’s construction schedule for the Work. The schedule shall not exceed time limits current
§ 9.8.2 The Contractor shall perform the Work in general accordance with the most recent schedule submitted to the Owner and Architect.
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 7.8.1 The Contractor, promptly after executing a Work Order, shall submit for the Owner's and Architect's information a Contractor's construction schedule for the Work described in that Work Order. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
§ 7.8.2 The Contractor shall perform the Work in general accordance with the most recent schedule submitted to the Owner and Architect.
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Project Schedule is attached to the Agreement as an exhibit. The Project Schedule shall not be extended without the prior review and approval of the Owner and the Architect. Contractor acknowledges and agrees that it has prepared and is fully familiar with the Project Schedule, which is a critical element of its Agreement with the Owner, and agrees to be bound thereby.
§ 3.10.1.1 The Contractor shall on each business day prepare a daily force and activity report on a form approved by the Owner which Contractor shall make available for Owner' s review, copying and inspection at all reasonable times.
§ 3.10.2 The Contractor shall prepare a submittal schedule, promptly after being awarded the Contract and shall update the same as necessary to maintain a current submittal schedule, and shall submit the schedule(s) for the Architect’s approval, which shall not unreasonably be delayed or withheld. The submittal schedule shall (1) be coordinated with the Contractor’s construction schedule, and (2) allow the Architect no less than fourteen (14) calendar days to review submittals. If the Contractor fails to submit a submittal schedule, the Contractor shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals.
§ 3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect as required to complete the Work within the Contract Time and as required by the Contract Documents. The schedule for the Work shall be maintained and updated monthly (or more frequently if the Owner reasonably determines that it is necessary) in such form (e.g. bar chart, CPM) and shall contain such information as the Owner and Architect may reasonably request. In addition, if requested by the Owner or Architect, the Contractor shall provide such additional information (such as daily force and activity reports, material purchase and delivery status reports and reports of progress against schedule milestones) as are reasonably necessary to monitor the status of the Work and respond to any delays thereto. Contractor shall also provide Owner with reasonable advance notice, whenever practicable, of the completion of various milestones and or Phases prior to their actual completion (for instance, if Contractor assumes the completion of the then-current phase within the next thirty (30) days, Contractor should specifically apprise the Owner o...
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
3.10.2 The Contractor shall prepare and keep current, for the Architect's approval, a schedule of submittals which is coordinated with the Contractor's construction schedule and allows the Architect reasonable time to review submittals.
3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect.
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Construction Schedule shall be a detailed schedule for the Work based on the critical path method listing the relative precedence of construction activities on the critical path and float times for non-critical activities. Such Schedule shall also include Milestone Dates as designated by the Owner. Time is of the essence of the Contract. The Owner’s approval shall not signify the feasibility or correctness of the Construction Schedule. Within ten days following approval of the Construction Schedule, the Contractor shall furnish the Owner with an estimated cash flow schedule showing anticipated monthly expenditures throughout the duration of the Contract Time based on the Appendix A Schedule of Values.
3.10.2 The Contractor shall prepare and keep current, for the Architect’s approval, a schedule of submittals which is coordinated with the Construction Schedule and allows the Architect reasonable time to review submittals.
3.10.3 The Contractor shall perform the Work in accordance with the Construction Schedule, as the same may from time to time be modified by Change Order.
3.10.4 The Contractor shall monitor the progress of the Work for conformance with the requirements of the Construction Schedule and shall promptly advise the Owner of any delays or potential delays. If any activities on the critical path fall behind, within three (3) days the Contractor will notify the Owner and will with such notice furnish a reasonably detailed plan showing the measures which will promptly be taken by the Contractor to bring activities on the critical path back onto the Construction Schedule (“Corrective Plan”), all without change to the Contract Sum or Contract Time except as otherwise provided in Section 8.3.1. Such measures to correct the delay shall include overtime and/or additional labor, if necessary. The Corrective Plan shall indicate the date by which the progress of the Work will return to compliance with the critical path of the Construction Schedule and shall be subject to the approval of the Owner and the Architect. In no event shall any Corrective Plan constitute an adjustment in the Construction Schedule, Contract Time or any Milestone Date unless any such adjustment is authorized pursuant to a Change Order, nor shall the Construction Schedule, Contract Time or any Milestone Date be adjusted without a Change Order.
3.10.5 In the event that (i) the performance of the Work, as of a Milestone Date, has not progressed or reached the level of comple...
CONTRACTOR’S CONSTRUCTION SCHEDULES. The CM shall provide a copy of the Master Schedule to the bidders. As part of the notice of award of each contract, the CM shall inform each Contractor of the requirements for the preparation of a construction schedule. The Contractor shall prepare its own construction schedule in accordance with the requirements of the Contract Documents. The Contractor's Construction Schedule shall establish completion dates that comply with the requirements of the Master Schedule. The CM shall review each Contractor’s Construction Schedule and shall verify that the schedule is prepared in accordance with the requirements of the Contract Documents and that it establishes completion dates that comply with the requirements of the Master Schedule.
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly (within thirty 30 days) after notification of contract award, shall prepare and submit for the Owner’s and Architect’s information a Contractor’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised monthly or at appropriate intervals as required by the conditions of the Work and Project whichever is less, shall be related to the entire Project to the extent required by the Contract Documents and shall provide for expeditious and practicable execution of the Work.
3.10.1.1 Owner may authorize construction activities to commence prior to completion of Drawings and Specifications. If Drawings and Specifications require further development at the time the initial construction schedule is prepared, Contractor shall: 1) allow time in the schedule for further development of Drawings and Specifications by Architect, including time for review by Owner and Contractor and for Contractor’s coordination of Subcontractors’ Work, and 2) furnish to Owner, in a timely manner, information regarding anticipated market conditions and construction cost, availability of labor, materials and equipment, and proposed methods, sequences and time schedules for construction of Work.
3.10.2 The Contractor shall prepare and keep current, for the Architect's approval, a schedule of submittals which is coordinated with the Contractor's construction schedule and allows the Architect reasonable time, as defined by the Architect to review submittals. If the Contractor fails to submit a schedule, the Contractor shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals.
3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect.
3.10.4 Owner shall not be bound by any early completion deadline submitted in any schedule.
3.10.5 Owner does not approve or accept any schedule, but reserves the right to review, comment and reject.
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Contractor, shall at the times designated in the Agreement, prepare and submit for the Owner’s and
§ 3.10.2 The Contractor shall at the times designated in the Agreement, prepare a submittal update such schedule as necessary to maintain a current submittal schedule, and shall subm Architect’s approval. The Architect’s approval shall not unreasonably be delayed or withhel shall (1) be coordinated with the Contractor’s construction schedule, and (2) allow the Arch
§ 3.10.3 The Contractor shall perform the Work in general accordance with the most recent approved schedules.
§ 3.10.4 The Contractor shall schedule and conduct progress meetings at the site on a bi-weekly basis (or interval appropriate for the level of job site activity). Attendance is required of each Subcontractor, Supplier, or other entity concerned with current progress or planning future activities. Owner and Architect. shall be notified of meeting dates and times.