Applications for Payments Clause Samples
Applications for Payments. A. Contractor shall submit an application for payment in a form acceptable to the Engineer, no more frequently than monthly, to Engineer. Applications for payment will be prepared and signed by Contractor. Contractor shall provide supporting documentation required by the Contract Documents. Payment will be paid for Work completed as of the date of the application for payment.
B. Beginning with the second application for payment, each application shall include an affidavit of Contractor stating that all previous progress payments received on account of the Work have been applied on account to discharge Contractor’s legitimate obligations associated with prior applications for payment.
Applications for Payments. 1. At least 20 days before the date estab- lished for each progress payment (but not more often than once a month), CONTRACTOR shall submit to ENGINEER for review an Application for Payment filled out and signed by CONTRACTOR covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Docu- ments. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Applica- tion for Payment shall also be accompanied by a bill of sale, invoice, or other documentation warranting that OWNER has received the materials and equip- ment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance or other arrangements to protect OWNER’s interest therein, all of which must be satisfactory to OWNER.
2. Beginning with the second Application for Payment, each Application shall include an affidavit of CONTRACTOR stating that all previous progress payments received on account of the Work have been applied on account to discharge CONTRACTOR’s legitimate obligations associated with prior Applications for Payment.
3. The amount of retainage with respect to progress payments will be as stipulated in the Agreement.
Applications for Payments. 1. Contractor is responsible for providing all information as required to become a vendor of the City.
2. At least 20 days before the date established in the General Requirements for each progress payment, Contractor shall submit to City for review an Application for Payment filled out and signed by Contractor covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents.
3. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a ▇▇▇▇ of sale, invoice, or other documentation warranting that City has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate insurance or other arrangements to protect City’s interest therein, all of which must be satisfactory to City.
4. Beginning with the second Application for Payment, each Application shall include an affidavit of Contractor stating that previous progress payments received on account of the Work have been applied on account to discharge Contractor’s legitimate obligations associated with prior Applications for Payment.
5. The amount of retainage with respect to progress payments will be as stipulated in the Contract Documents.
Applications for Payments. 1. At least 20 days before the date established in the Agreement for each progress payment (but not more often than once a month), Contractor shall submit to Engineer for review an Application for Payment filled out and signed by Contractor covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents.
2. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment must also be accompanied by: (a) a bill of sale, invoice, copies of subcontract or purchase order payments, or other documentation establishing full payment by Contractor for the materials and equipment; (b) at Owner’s request, documentation warranting that Owner has received the materials and equipment free and clear of all Liens; and (c) evidence that the materials and equipment are covered by appropriate property insurance, a warehouse bond, or other arrangements to protect Owner’s interest therein, all of which must be satisfactory to Owner.
3. Beginning with the second Application for Payment, each Application must include an affidavit of Contractor stating that all previous progress payments received by Contractor have been applied to discharge Contractor’s legitimate obligations associated with prior Applications for Payment.
4. The amount of retainage with respect to progress payments will be as stipulated in the Agreement.
Applications for Payments. A. The CONTRACTOR shall submit to the COUNTY for review, an Application for Payment filled out and signed by the CONTRACTOR covering the Work completed as of the date of the Application and accompanied by such supporting documentation as required by the Contract Documents. Such supporting documents shall include but not be limited to: (i) a current release from the CONTRACTOR releasing all claims, other than those previously submitted pursuant to Article 10 herein, through the date of the Application for Payment; and (ii) a monthly dated Critical Path Method (CPM) Schedule for the Project. Written consent from the surety in a form acceptable to the County regarding the project or payment may be given in lieu of waivers. Submission of this supporting documentation shall be a condition precedent to the CONTRACTOR’s entitlement to receive payment. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice, or other documentation warranting that the COUNTY has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance or other arrangements to protect the COUNTY’s interest therein, all of which must be satisfactory to the COUNTY.
B. Beginning with the second Application for Payment, each Application shall include:
(i) an affidavit by the CONTRACTOR stating that all previous progress payments received on account of the Work have been applied on account to discharge the CONTRACTOR’s legitimate obligations associated with prior Applications for Payment and
(ii) a “Conditional Waiver of Right to Claim Against Payment Bond and ▇▇▇▇▇▇▇▇▇ County” completed by the CONTRACTOR and all subcontractors.
C. Pursuant to Section 255.078(1), Fla. Stat., the COUNTY will withhold from each progress payment made to the CONTRACTOR the amount of 5% of the payment as retainage. Pursuant to Section 255.078(3), Fla. Stat., the COUNTY may elect not to pay or release any amounts (such as retainage) that are the subject of a good faith dispute in writing, the subject of a claim brought pursuant to Section 255.05, Fla. Stat., or otherwise the subject of a claim or demand by the COUNTY or CONTRACTOR.
D. The Application for Final Payment shall be made after the CONTRACTOR has, in the opinion o...
Applications for Payments. At least 20 days before the date established for each progress payment (but not more often than once a month), CONTRACTOR shall submit to Owner’s Representative for review an Application for Payment filled out and signed by CONTRACTOR covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice, or other documentation warranting that OWNER has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance or other arrangements to protect OWNER’s interest therein, all of which must be satisfactory to OWNER.
Applications for Payments. 1. At least 20 days before the date established in the Agreement for each progress payment to be paid by Owner (but not more often than once a month), Construction Manager shall submit to Architect and Owner for review an Application for Payment on AIA forms G702 and G703 and filled out and signed by Construction Manager based on the completion and progress of the, and for Unit Price Work, based on the number of units completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. For the Unit Price Work, Construction Manager shall not be entitled to payment for the performance of any quantities of the Unit Price Work unless prior to performing same the quantities are verified and approved, in writing, by the Architect. If the Construction Manager proceeds with any Unit Price Work without obtaining the prior written approval of the Architect, the Construction Manager shall not be entitled to payment for the performance of such Unit Price Work. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a ▇▇▇▇ of sale, invoice, or other documentation warranting that Owner has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance or other arrangements to protect Owner’s interest therein, all of which must be satisfactory to Owner. Notwithstanding the foregoing, each Application for Payment shall show a complete breakdown of the Project components, the quantities completed and the amounts due, together with such data substantiating the Construction Manager’s right to payment and such supporting evidence which may be requested by the Architect or Owner including, but not limited to: (a) all Subcontractor requisitions, receipted invoices, delivery invoices; (b) where required by any manufacturers for extended warranties, inspection certificates or other acceptable documentation confirming the acceptable completion of any and all required inspections for the Work performed for which payment is being made; (c) all monthly reports required by any federal, state or local requirements including, but not limited to ▇▇▇▇▇-▇▇▇▇▇; and (d) any other documentation requested by Owner to support the amounts for the Cost of th...
Applications for Payments. A. The contractor shall submit signed applications for payment to the Engineer monthly, in a form acceptable to the Engineer. Contractor shall provide supporting documentation required by the Contract Documents. Owner will pay for Work completed as of the date of the application for payment.
B. Applications for payment must be accompanied by a progress report identifying all of the septic tanks pumped during the pay period with customers addresses and the completed inspection forms.
Applications for Payments. A. Contractor shall submit an application for payment in a form acceptable to the Project Manager, no more frequently than monthly, to Project Manager. Applications for payment will be prepared and signed by Contractor. Contractor shall provide supporting documentation required by the Contract Documents. Payment will be paid for Work completed as of the date of the application for payment.
B. Beginning with the second application for payment, each application shall include an affidavit of Contractor stating that all previous progress payments received on account of the Work have been applied on account to discharge Contractor’s legitimate obligations associated with prior applications for payment. Owner may, in its discretion, require interim releases from Contractor and its subcontractors and suppliers.
Applications for Payments. 1. At least 20 days before the date established in the Agreement for each progress payment (but not more often than once a month), Contractor shall submit to Engineer for review an Application for Payment filled out and signed by Contractor covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a ▇▇▇▇ of sale, invoice, or other documentation warranting that Owner has received the materials and equipment free and clear of all Liens, and evidence that the materials and equipment are covered by appropriate property insurance, a warehouse bond, or other arrangements to protect Owner’s interest therein, all of which must be satisfactory to Owner.
2. Beginning with the second Application for Payment, each Application shall include an affidavit of Contractor stating that all previous progress payments received on account of the Work have been applied on account to discharge Contractor’s legitimate obligations associated with prior Applications for Payment.
3. The amount of retainage with respect to progress payments will be as stipulated in the Agreement.