Examples of Subcontract Sum in a sentence
In the event of suspension ordered by the Contractor, the Subcontractor shall be entitled to an equitable adjustment of the Subcontract Time and Subcontract Sum.
Such payment to the Subcontractor shall be the entire unpaid balance of the Subcontract Sum if a full release of retainage is allowed under the Prime Contract for the Subcontractor’s Work prior to the completion of the entire Project.
If the unpaid balance of the Subcontract Sum exceeds the expense of finishing the Subcontractor’s Work and other damages incurred by the Contractor and not expressly waived, such excess shall be paid to the Subcontractor.
If such expense and damages exceed the unpaid balance of the Subcontract Sum, the Subcontractor shall pay the difference to the Contractor.
The Subcontract Sum shall, by appropriate Modification, be increased by the amount of the Subcontractor’s reasonable costs of demobilization, delay and remobilization.