Mechanical Completion Date definition

Mechanical Completion Date means the date on which Mechanical Completion occurs.
Mechanical Completion Date means the date that Client makes the Mechanical Completion payment (Payment #4 in Schedule #6) to EPC Contractor, which will be no later than the date set forth in the Project Schedule provided that Client has approved, or otherwise indicated any required changes and reasonable basis for same, all in accordance with this Agreement.
Mechanical Completion Date has the meaning set forth in Section 6.2.3.

Examples of Mechanical Completion Date in a sentence

  • At least twenty-one (21) days, but no more than thirty-five (35) days, prior to the date on which Seller anticipates the Work will achieve Mechanical Completion (the “Anticipated Mechanical Completion Date”), Seller shall provide to Buyer written notice of the Anticipated Mechanical Completion Date.

  • The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.

  • The relevant portions of Article 3.3 state:3.3.2 Contractor shall achieve Mechanical Completion no later than the Scheduled Mechanical Completion Date and Construction Completion no later than the Scheduled Construction Completion Date.

  • If this Agreement is terminated prior to the Project Mechanical Completion Date, Contractor shall furnish Owner with any and all final documents which have been prepared, and the most up-to-date versions of documents which are not yet final.

  • Therefore, the Parties have agreed to quantify and to agree upon such damages in advance.3.3.3 In the event Contractor fails to achieve (a) Mechanical Completion by the Scheduled Mechanical Completion Date or (b) Construction Completion by the Scheduled Construction Completion Date, in either case, Contractor agrees to pay Covanta as liquidated damages (and not as a penalty nor subject to any proof of such loss)Contract art.


More Definitions of Mechanical Completion Date

Mechanical Completion Date means the date on which Mechanical Completion for each turbine is demonstrated in accordance with the requirements of Section 20.1.
Mechanical Completion Date means the date on which Gevo determines that the Facility has achieved Mechanical Completion.
Mechanical Completion Date means the date Mechanical Completion is confirmed as described in Section 5.1.
Mechanical Completion Date shall have the meaning ascribed to it in the Engineering and Construction Agreement.
Mechanical Completion Date means the actual date of achieving Mechanical Completion as determined pursuant to Section 11.1.
Mechanical Completion Date means the date on which Mechanical Completion actually occurs, as determined in the manner set forth in Section 11.1(e).
Mechanical Completion Date means the date which Supplier and Supplier's construction contractor agree is the date that the Facility has been completed to the extent necessary to begin start-up and performance testing.