Inexcusable Delay definition

Inexcusable Delay means any delay of the completion of the Project beyond the expiration of the Contract Time resulting from causes other than those listed above. An Inexcusable Delay shall not entitle the Contractor to an extension of the Contract Time or an adjustment of the Contract Sum.
Inexcusable Delay means any delay beyond the Contract Time resulting from causes other than those listed in Subparagraphs A1 and A2, above. An Inexcusable Delay will not entitle the Contractor to an extension of Contract Time or an adjustment of the Contract price.
Inexcusable Delay means any delay that adversely impacts the critical path of the Work resulting from causes other than those listed in Subparagraphs (a)(1) or and (a)(2) above due to the acts or omissions of Contractor or its Subcontractors. An Inexcusable Delay will not entitle Contractor to an extension of the Term of this Facilities Lease or an adjustment of the GMP.

Examples of Inexcusable Delay in a sentence

  • If an Inexcusable Delay occurs concurrently with either an Excusable Delay and/or a Compensable Delay, the maximum extension of time shall be the number of days, if any, bywhich the duration of the Excusable Delay and/or the Compensable Delay exceeds the Inexcusable Delay.


More Definitions of Inexcusable Delay

Inexcusable Delay means any delay in completion of the Work beyond the expiration of the Contract
Inexcusable Delay means delay for which the Contractor is not entitled to a time extension or monetary compensation and may even be liable in damages to the Owner.
Inexcusable Delay means any delay in completion of the Work beyond the expiration of the 33 Contract Time resulting from causes other than those listed in Subparagraphs A1 and A2, above.
Inexcusable Delay. Has the meaning assigned to it in Section 10.4.
Inexcusable Delay has the meaning assigned to it in Clause 13.1.
Inexcusable Delay has the meaning set forth in Section 20.10.
Inexcusable Delay means any delay in Substantial Completion or Final Completion of the Work resulting from causes other than those which are excusable or compensable pursuant to Section 20.9 and 20.10. An Inexcusable Delay shall not entitle the Architect or the CM/GC to an extension of the Contract Time or any adjustment of the Allowable Cost, the Expected Cost, the Target Cost or the EMP.