Examples of Date for Completion in a sentence
We agree that the Alliance Works must be executed to achieve Completion by the Date for Completion.
The Date for Completion (settlement) is 30 Working Days after the date First Grant Contracts are exchanged (being the date an Option is exercised), or as specified in the First Grant Contract.
The Supplier’s obligation to achieve Completion by the Date for Completion is paramount and this clause 23.12 is to be construed so as not to derogate from this obligation.
If the Contractor fails to comply with Clause21.5, the Contractor will have no entitlement to an extension of time of the Date for Completion.
If the Principal considers (acting reasonably) that the Contractor is not entitled to an extension of time, the Principal’s Representative must notify the Contractor within 10 Business Days (or any other period agreed in writing by the Parties) of receipt of the claim under Clause 21.5 that the Date for Completion remains unchanged.