Re: PJM Interconnection, L.L.C.; Docket No. ER23-1906-000 Original Service Agreement No. 6904; Queue No. AC2-157
Service Agreement • May 16th, 2023

Pursuant to section 205 of the Federal Power Act,1 Part 35 of the rules and regulations of the Federal Energy Regulatory Commission (“Commission”),2 and PJM Open Access Transmission Tariff, Part VI (“Tariff”), PJM Interconnection, L.L.C. (“PJM”) submits for filing an executed Interconnection Service Agreement (“ISA”) among PJM, Trade Post Solar LLC (“Interconnection Customer”), and Indiana Michigan Power Company (“Interconnected Transmission Owner”) (the “Trade Post ISA”).3 PJM requests an effective date of April 17, 2023 for the Trade Post ISA, designated as Original Service Agreement No. 6904.4

AutoNDA by SimpleDocs
INTERCONNECTION SERVICE AGREEMENT Among
Service Agreement • September 23rd, 2022
INTERCONNECTION SERVICE AGREEMENT Among
Service Agreement • September 5th, 2022
INTERCONNECTION SERVICE AGREEMENT Among
Service Agreement • July 27th, 2022
FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • June 7th, 2022

On April 13, 2022, PJM Interconnection, L.L.C. (PJM) filed an executed Interconnection Service Agreement (ISA) among PJM, Sloopy Solar Energy LLC (Sloopy Solar) and American Transmission System, Inc., designated as Service Agreement No. 6393.1 PJM states that it is submitting the ISA because it adds a schedule of charges, that does not conform to the form of the ISA set forth in Attachment O of the PJM Open Access Transmission Tariff. PJM requests that the ISA be accepted effective March 14, 2022.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • June 1st, 2022

On January 27, 2022, PJM Interconnection, L.L.C. (PJM), filed an executed Interconnection Service Agreement (ISA) among PJM, Cottontail Solar 3, LLC, and PPL Electric Utilities Corporation, designated as Service Agreement No. 6315.1 PJM states that it is submitting the ISA because it contains a schedule of charges that does not conform to the form of the ISA set forth in Attachment O of the PJM Open Access Transmission Tariff. PJM requests that the ISA be accepted effective December 29, 2021.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • May 19th, 2022

On May 19, 2022, PJM Interconnection, L.L.C. (PJM) filed an executed Interconnection Service Agreement (ISA) among PJM, Ross County Solar, LLC and AEP Ohio Transmission Company, Inc, designated as Service Agreement No. 6540.1 PJM states that it is submitting the ISA because it contains a power factor requirement that does not conform to the form of the ISA set forth in Attachment O of the PJM Open Access Transmission Tariff. PJM requests that the ISA be accepted effective April 19, 2022.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • May 11th, 2022

On March 10, 2022, PJM Interconnection, L.L.C. (PJM) filed (i) an Interconnection Service Agreement (ISA) and (ii) an Interconnection Construction Service Agreement (ICSA), both among PJM, Pitt Solar, LLC (Interconnection Customer), and Virginia Electric and Power Company (Interconnected Transmission Owner) (the Pitt Solar ISA and Pitt Solar ICSA respectively, and, collectively, the Pitt Solar Agreements), designated as Service Agreement Nos. 6372 and 6373, respectively.1 PJM states that it is filing the Pitt Solar Agreements because the Pitt Solar ISA contains a Schedule of Charges, and the Pitt Solar ISA and Pitt Solar ICSA each contains non- standard terms and conditions as well as other provisions that do not conform to the forms of ISA and ICSA set forth in Attachment O and Attachment P, respectively, of the PJM Open Access Transmission Tariff. PJM requests effective dates of February 10, 2022 and February 17, 2022 for the Pitt Solar ISA and Pitt Solar ICSA, respectively.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • March 28th, 2022

Reference: Interconnection Service Agreement No. 6380 and Notice of Cancellation of Interim Interconnection Service Agreement No. 5142

Document Accession #: 20220428-3071 Filed Date: 04/28/2022
Service Agreement • March 2nd, 2022

This action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided for in the filed document(s); nor shall such action be deemed as recognition of any claimed contractual right or obligation affecting or relating to such service or rate; and such action is without prejudice to any findings or orders which have been or may hereafter be made

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • February 24th, 2022

On January 20, 2022, PJM Interconnection, L.L.C. (PJM) submitted an Interconnection Service Agreement among PJM, Bellflower Solar 1, LLC (Bellflower), and AEP Indiana Michigan Transmission Company, Inc. (AEP) (the Bellflower ISA).1 The Bellflower ISA replaces the Interim Interconnection Service Agreement among PJM, Bellflower and AEP (the Parties), designated as Service Agreement No. 6014.2 Since the January 20 Filing, the Parties identified inaccurate information in the as-filed Bellflower Solar ISA, which PJM corrected in its revised filing.3 Pursuant to the authority delegated to the Director, Division of Electric Power Regulation – East, under 18 C.F.R.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • February 17th, 2022

On February 17, 2022, you filed, on behalf of PJM Interconnection, L.L.C. (PJM), an executed Interconnection Service Agreement (ISA) among PJM, Calpine Mid-Atlantic Development, LLC (Calpine), and Atlantic City Electric Company, designated as Service Agreement No. 1767.1 You state that PJM is submitting the ISA because it contains terms and conditions, including a schedule of charges, that does not conform to the form of the ISA set forth in Attachment O of the PJM Open Access Transmission Tariff. PJM requests that the ISA be accepted effective January 19, 2022.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • December 22nd, 2021

Pursuant to the authority delegated to the Director, Division of Electric Power Regulation – East, under 18 C.F.R. § 375.307 (2021), your submittal is accepted for filing, effective November 23, 2021, as requested.2

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • December 14th, 2021

This action is taken pursuant to authority delegated to the Director, Division of Electric Power Regulation – East, under 18 C.F.R. § 375.307 (2021).

AutoNDA by SimpleDocs
FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • November 19th, 2021

On November 19, 2021, you submitted on behalf of PJM Interconnection, L.L.C. (PJM) an Interconnection Service Agreement (ISA) among PJM, Renovo Energy Center LLC, as Interconnection Customer, and Mid-Atlantic Interstate Transmission, LLC (MAIT), as Interconnected Transmission Owner, designated as Service Agreement No. 6225.1 You state that the ISA contains provisions that do not conform to the ISA Form. You request that the ISA be accepted effective October 20, 2021. Pursuant to authority delegated to the Director, Division of Electric Power Regulation – East, under 18 C.F.R.

INTERCONNECTION SERVICE AGREEMENT By and Among
Service Agreement • November 12th, 2021
Document Accession #: 20211217-3025 Filed Date: 12/17/2021‌‌
Service Agreement • October 20th, 2021

On October 29, 2021, you filed on behalf of PJM Interconnection, L.L.C. (PJM) an amended Interconnection Service Agreement (ISA) among PJM, Crescent Ridge LLC (Crescent Ridge), and Commonwealth Edison Company (Amended Crescent Ridge ISA).1 The Amended Crescent Ridge ISA reflects modifications to the Customer Facility’s wind turbines and other changes.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • September 30th, 2021

On September 29, 2021, PJM Interconnection, L.L.C. (PJM) submitted an Interconnection Service Agreement (ISA) among PJM, High Point Solar LLC

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • September 29th, 2021

This action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided for in the filed document(s); nor shall such action be deemed as recognition of any claimed contractual right or obligation affecting or relating to such service or rate; and such action is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against the applicant(s).

Original Service Agreement No. 6182; Queue No. AD2-163
Service Agreement • September 24th, 2021

Pursuant to section 205 of the Federal Power Act,1 Part 35 of the rules and regulations of the Federal Energy Regulatory Commission (“Commission”),2 and PJM Open Access Transmission Tariff, Part VI (“Tariff”), PJM Interconnection, L.L.C. (“PJM”) submits for filing an executed Interconnection Service Agreement (“ISA”) among PJM, Madison Fields Solar Project, LLC (“Interconnection Customer”), and the American Transmission Systems, Inc. (“Interconnected Transmission Owner”) (the “Madison Fields ISA”).3 PJM requests an effective date of August 25, 2021 for the Madison Fields ISA, designated as Service Agreement No. 6182.

INTERCONNECTION SERVICE AGREEMENT Among
Service Agreement • September 13th, 2021
FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • September 10th, 2021

On September 10, 2021, PJM Interconnection, L.L.C. (PJM) filed an executed Interconnection Service Agreement (ISA) by and among PJM, Marion County Solar Project, LLC and American Transmission Systems, Incorporated, designated as Service Agreement No. 6169.1 PJM states that it is submitting the ISA because it contains a schedule of charges that does not conform to the form of ISA set forth in Attachment O to the PJM Open Access Transmission Tariff. PJM requests that the ISA be accepted effective August 11, 2021.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • September 8th, 2021

On September 8, 2021, PJM Interconnection, L.L.C. (PJM) submitted an executed Interconnection Service Agreement (ISA) among PJM as Transmission Provider, Cape Solar, LLC as Interconnection Customer, and The Potomac Edison Company as Interconnected Transmission Owner, designated as Original Service Agreement No.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • August 20th, 2021

On August 16, 2021, as amended on August 24, 2021, PJM Interconnection, L.L.C (PJM) filed an executed Interconnection Service Agreement (ISA) among, Walnut Solar I, LLC (Walnut Solar), and Virginia Electric and Power Company (Virginia Power), designated as Third Revised Service Agreement No. 5481 (Walnut Solar ISA).1 You state that the Walnut Solar ISA contains terms and conditions that do not conform to the applicable form of ISA set forth in Attachment O of the PJM Open Access Transmission Tariff. In Docket No. ER21-2694-001, PJM filed an amendment,2 which modifies the Walnut Solar ISA to accommodate the assignment of all of Walnut’s Solar’s rights and delegation of all of its duties under the Walnut Solar ISA to Virginia Power. PJM requests that the amended Walnut Solar ISA be accepted effective July 16, 2021.

Re: PJM Interconnection, L.L.C.; Docket No. ER21-ER21-2740-000 Original Service Agreement No. 6154; Queue No. AE1-185
Service Agreement • August 18th, 2021

Pursuant to section 205 of the Federal Power Act,1 Part 35 of the rules and regulations of the Federal Energy Regulatory Commission (“Commission”),2 and PJM Open Access Transmission Tariff, Part VI (“Tariff”), PJM Interconnection, L.L.C. (“PJM”) submits for filing an executed Interconnection Service Agreement (“ISA”) among PJM, Cottontail Solar I, LLC (“Interconnection Customer”), and Mid-Atlantic Interstate Transmission, LLC (“Interconnected Transmission Owner”) (the “Cottontail ISA”).3 PJM requests an effective date of July 27, 2021 for the Cottontail ISA, designated as Service Agreement No. 6154.

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426
Service Agreement • July 29th, 2021

On July 29, 2021, you filed on behalf of PJM Interconnection, L.L.C. (PJM), an amended Interconnection Service Agreement (ISA) among PJM, Oak Trail Solar, LLC (Oak Trail Solar) and Virginia Electric and Power Company, designated as Service Agreement No. 5995.1 You state that the amended ISA modifies Service Agreement No. 5995, which was previously accepted by the Commission in Docket No. ER21-1578- 000,2 to update Oak Trail Solar’s contact information and to correct the location of the customer facility. PJM requests that the effective date for the amended ISA remain unchanged at March 3, 2021.