Common use of Nitrogen Clause in Contracts

Nitrogen. Until Substantial Completion of Subproject 2, Contractor shall provide all nitrogen as required for construction, testing, drying, purging and commissioning, including the Tanks.

Appears in 5 contracts

Samples: Escrow Agreement (Sabine Pass Liquefaction, LLC), Engineering, Procurement and Construction Agreement (Cheniere Energy Inc), Escrow Agreement (Cheniere Energy Partners LP Holdings, LLC)

AutoNDA by SimpleDocs

Nitrogen. Until Substantial Completion of Subproject 23, Contractor shall provide all nitrogen as required for construction, testing, drying, purging and commissioning, including the Tanks.

Appears in 4 contracts

Samples: Procurement and Construction Agreement (Cheniere Corpus Christi Holdings, LLC), Procurement and Construction Agreement (Corpus Christi Pipeline GP, LLC), Procurement and Construction Agreement (Cheniere Energy Inc)

Nitrogen. Until Substantial Completion of Subproject 24, Contractor shall provide all nitrogen as required for construction, testing, drying, purging and commissioning, including the Tanks.

Appears in 3 contracts

Samples: Escrow Agreement (Sabine Pass Liquefaction, LLC), Escrow Agreement (Cheniere Energy Partners LP Holdings, LLC), Escrow Agreement (Cheniere Energy Partners, L.P.)

AutoNDA by SimpleDocs

Nitrogen. Until Substantial Completion of Subproject 25, Contractor shall provide all nitrogen as required for construction, testing, drying, purging and commissioning, including the Tanks.

Appears in 2 contracts

Samples: Escrow Agreement (Cheniere Energy Partners, L.P.), Escrow Agreement (Cheniere Energy Partners, L.P.)