Review Stages. The Architect/Engineer shall submit documents to the Owner for review at completion of the Schematic Design Phase, Design Development Phase and at the following stages of completion of the Construction Documents Phase as follows: 50%, 100% The following Exhibits are fully incorporated into this Agreement by reference: EXHIBITS Ex A Personnel Titles and Hourly Rates Ex B BIM Execution Plan EXHIBIT A PERSONNEL TITLES AND HOURLY RATES The prime architectural or engineering firm for this project will assemble the following information from consulting team members associated with the project. The categories of personnel indicated should be edited to include only those expected to be actually working on this project. When preparing this schedule, you are expected to adhere to the position classifications and titles presented to the greatest extent possible. Additional consultant listings and/or position classifications may be added as needed or required by the project. FU irm/Position Classification UHourly Billing Rate Architecture – SmithGroup, Inc. Principal $250.00 Design Principal $260.00 Project Manager $160.00 Project Architect I $ 95.00 Project Architect II $115.00 Project Architect III $145.00 Construction Administrator $200.00 Intern Architect $ 95.00 BIM/CADD Technician $ 95.00 Administrative Staff $ 85.00 MEP Engineering – SmithGroup, Inc. Principal $250.00 Senior Project Manager $205.00 Project Manager $160.00 Engineer IV $195.00 Engineer III $165.00 Engineer II $130.00 Engineer I $110.00 Engineering Designer IV $165.00 Engineering Designer III $135.00 Engineering Designer II $105.00 Engineering Designer I $110.00 Construction Administrator $200.00 BIM/CADD Technician $ 85.00 Administrative Staff $ 85.00 Structural Engineering - JQ Infrastructure, LLC Partner $260.00 Principal $225.00 Senior Project Manager $185.00 Engineering Technical Lead $195.00 Project Manager $160.00 Senior Engineer $145.00 Engineer $130.00 Senior BIM/CADD Technician $125.00 BIM/CADD Technician $ 95.00 Administrative Staff $ 80.00 Civil Engineering – Xxxxxxx Engineering Principal $200.00 Senior Project Manager $175.00 Project Manager $160.00 Senior Engineer $160.00 Engineer $135.00 Graduate Engineer $105.00 Engineering Designer $ 80.00 Construction Administrator $160.00 Administrative Staff $ 60.00 Landscape Architecture – SmithGroup, Inc. Principal $250.00 Landscape Architect IV $150.00 Landscape Architect III $125.00 Landscape Architect II $110.00 Landscape Architect I $ 85....
Review Stages. The Architect/Engineer shall submit documents to the Owner for review at completion of the Schematic Design Phase, Design Development Phase and at the following stages of completion of the Construction Documents Phase as follows 100% A/E -XXXX BIM Contract No. 5997 09/19 Project No. 18-3313 The following Exhibits are fully incorporated into this Agreement by reference: EXHIBITS Ex A Personnel Titles and Hourly Rates Ex B BIM Execution Plan EXHIBIT A PERSONNEL TITLES AND HOURLY RATES The prime architectural or engineering firm for this project will assemble the following information from consulting team members associated with the project. The categories of personnel indicated should be edited to include only those expected to be actually working on this project. When preparing this schedule, you are expected to adhere to the position classifications and titles presented to the greatest extent possible. Additional consultant listingsand/or position classifications may be added as needed or required by the project. UFirm/Position Classification ourly Billing Rate Architecture Xxxxxxx Xxxxx Architects, Inc. Founding Principal $ 300.00/hour Principal $ 250.00/hour Sr. Vice President $ 225.00/hour Vice President/PM $ 200.00/hour Project Architect $ 175.00/hour Staff Architect $ 165.00/hour Visualization Renderer $ 165.00/hour Interior Designer $ 165.00/hour Administrative Staff $ 95.00/hour MEP Engineering Acts 29 Consulting/ME Engineers Principal $ 300.00/hour Associate Principal $ 280.00/hour Senior Project Manager $ 215.00/hour Project Manager $ 205.00/hour Senior Engineer $ 190.00/hour Engineer $ 160.00/hour Graduate Engineer $ 160.00/hour Engineering Designer $ 160.00/hour Construction Administrator $ 115.00/hour BIM/CADD Technician $ 115.00/hour Administrative Staff $ 110.00/hour Structural Engineering AG&E Structural Engenuity Managing Principal $ 335.00/hour Principal/Director $ 295.00/hour Associate/Senior Project Manager $ 265.00/hour Professional Engineer $ 210.00/hour Structural Dynamics Specialist $ 210.00/hour LiDAR $ 195.00/hour Quality Assurance $ 185.00/hour Engineer (Graduate or Certified) $ 145.00/hour Senior BIM Technician $ 145.00/hour Junior BIM/CADD Technician $ 95.00/hour Administrative and Billing $ 95.00/hour Clerical $ 65.00/hour Data/Telecommunications Consultant DataCom Design Group Principal $_198.00/hour_ Associate $_186.00/hour_ Senior Consultant $_160.00/hour_ Consultant $_138.00/hour_ Contract Administrator $_ 98.00/hour_ BIM/C...
Review Stages. The PSProvider shall submit documents to the Owner for review at completion of the Schematic Design Phase (if applicable), Design Development Phase and at the following stages of completion of the Construction Documents Phase as follows: 60%, 100%
Review Stages. The Architect/Engineer shall submit documents to the Owner for review at completion of the Schematic Design Phase, Design Development Phase and at the following stages of completion of the Construction Documents Phase as follows: (25% DD for GMP) & 25%, 50%, 75%, 100%
Review Stages. The Professional Services Provider shall submit CADD files and documents to the Owner for review at completion of the Schematic Design Phase, Design Development Phase and at the following stages of completion of the Construction Documents Phase: 50%, 95%, 100% 14.7 Not Used
Review Stages. The Project Architect shall submit all Project documents to the Owner as searchable .PDF and their native produced file format for review at each Design Phase as follows: Schematic Design: 50% and 100% Design Development: 50% and 100% Construction Documents: 50%, 75% and 100%
AutoNDA by SimpleDocs
Review Stages. There shall be four (4) design reviews at a 30% design stage (inhouse meeting with COUNTY), 60% pre-agency design stage, a 90% design stage, and a Final submittal. The COUNTY shall be allotted five (5) working days for review of the 60% submittal, 90% submittal, and Final submittal. All CADD-produced drawings shall be 24” X 36” at a true scale. Submittals of plans and support documentation shall be made at the following stages of plans completion with the indicated number of copies.

Related to Review Stages

  • ADB’s Review of Procurement Decisions 9. All contracts procured under international competitive bidding procedures and contracts for consulting services shall be subject to prior review by ADB, unless otherwise agreed between the Borrower and ADB and set forth in the Procurement Plan. SCHEDULE 5