Common use of PROGRESS OF THE WORK Clause in Contracts

PROGRESS OF THE WORK. The Contractor shall provide sufficient labor, materials, facilities, and equipment and shall work such hours, including night shifts, overtime operations, Saturdays, Sundays and holidays, as may be necessary to insure the prosecution and completion of the Work or separable portions thereof, in accordance with the Guaranteed Project Schedule. If the progress of the Work falls behind or fails to proceed in accordance with the Guaranteed Project Schedule, or it becomes apparent to the Owner from the current schedule that the Work will not be substantially complete within the Contract Time (as adjusted by Owner approved Change Orders), in addition to the other requirements of the Contract and remedies available to the Owner, the Contractor agrees to take the following actions at no additional cost to the Owner to correct such tardiness:

Appears in 10 contracts

Samples: Owner Contractor Agreement, Contractor Agreement, imlive.s3.amazonaws.com

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.