Common use of CERTIFICATES FOR PAYMENT Clause in Contracts

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue a Certificate for Payment to the State, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her reasons for withholding a Certificate as provided in Subparagraph 9.6.1

Appears in 156 contracts

Samples: Vermont Contract, Vermont Contract, Vermont Contract

AutoNDA by SimpleDocs

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven three (3) business days after the receipt of the Contractor's completed Application proper application for Paymentpayment, either issue a Certificate for Payment to the StateOwner a certificate for payment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1subparagraph 9.5.1.

Appears in 16 contracts

Samples: Agreement, Agreement, Agreement

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding certification in whole or in part. The issuance of a Certificate as provided in Subparagraph 9.6.1of Payment will constitute a recommendation only by the Architect and not a legal, binding obligation on Owner.

Appears in 13 contracts

Samples: www.unlv.edu, www.unlv.edu, www.unlv.edu

CERTIFICATES FOR PAYMENT. 9.4.1 (a) The Architect Architect/Engineer will, within seven ten (10) days after the receipt of the Prime Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Prime Contractor, for such amount as the Architect Architect/Engineer determines is properly due, or notify the Prime Contractor and Owner in writing his or her of the Architect/Engineer’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1in:

Appears in 9 contracts

Samples: lfpubweb.cityofdenton.com, lfpubweb.cityofdenton.com, lfpubweb.cityofdenton.com

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.

Appears in 8 contracts

Samples: Agreement, www.spotsylvania.k12.va.us:443, Immunicon Corp

CERTIFICATES FOR PAYMENT. 9.4.1 15.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her and Owner of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 15.4.3.

Appears in 8 contracts

Samples: www.wiltonct.org, go.boarddocs.com, www.gov.bm

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.

Appears in 4 contracts

Samples: crdact.net, biznet.ct.gov, Indemnity Agreement

CERTIFICATES FOR PAYMENT. 9.4.1 14.2.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.114.2.3.

Appears in 3 contracts

Samples: www.rsfassociation.org, www.outagamie.org, www.dmhprojects.com

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the ContractorConstruction Manager's completed Application for Payment, either issue to the Development Manager a Certificate for Payment to the StatePayment, with a copy to the ContractorConstruction Manager, for such amount as the Architect determines is properly due, or notify the Contractor Construction Manager and Development Manager in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.

Appears in 2 contracts

Samples: Agreement (Chukchansi Economic Development Authority), Chukchansi Economic Development Authority

CERTIFICATES FOR PAYMENT. 9.4.1 15.2.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 15.2.3.

Appears in 2 contracts

Samples: themuseumschool.org, www.gov.bm

CERTIFICATES FOR PAYMENT. 9.4.1 (a) The Architect Architect/Engineer will, within seven ten (10) days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect Architect/Engineer determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect/Engineer’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1in

Appears in 2 contracts

Samples: Contract by and Between, lfpubweb.cityofdenton.com

CERTIFICATES FOR PAYMENT. 9.4.1 14.2.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.114.2.3.

Appears in 1 contract

Samples: Omtool LTD

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.

Appears in 1 contract

Samples: 70.248.29.17:8085

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven five (5) days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her reasons of the Architect's reason for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Paragraph 9.5.1.

Appears in 1 contract

Samples: Construction Contract (NightHawk Biosciences, Inc.)

CERTIFICATES FOR PAYMENT. 9.4.1 8.4.1 The Architect willwill promptly review such Application and, within seven days after the receipt of the Contractor's completed Application for Payment, either issue a Certificate for Payment to the StateOwner, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her reasons for withholding a Certificate as provided in Subparagraph 9.6.18.6.1.

Appears in 1 contract

Samples: Contractor Agreement (Wells Real Estate Investment Trust Inc)

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue Paym Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is Arc properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate as provided w in Subparagraph 9.6.1whole or in part. r of liens, claims,

Appears in 1 contract

Samples: www.gov.bm

CERTIFICATES FOR PAYMENT. 9.4.1 8.4.1 The Architect willwill promptly review such Application and, within seven days after the receipt of the Contractor's completed Application for Payment, either issue a Certificate for Payment to the StateOwner, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her reasons for withholding a Certificate as provided in Subparagraph 9.6.18.6.1

Appears in 1 contract

Samples: Owner Contractor Agreement (Wells Real Estate Fund Ix Lp)

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify notifY the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.

Appears in 1 contract

Samples: STAMPS.COM Inc

AutoNDA by SimpleDocs

CERTIFICATES FOR PAYMENT. § 9.4.1 The Architect will, within seven ten days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.

Appears in 1 contract

Samples: Agreement (Sierra Pacific Resources /Nv/)

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate as provided certification in Subparagraph 9.6.1whole or in part. men t in the manner payment from the nd contr

Appears in 1 contract

Samples: www.gov.bm

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to Arch ithh hitect to the Owner, r Paointsent Com the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate w in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.

Appears in 1 contract

Samples: bidcondocs.delaware.gov

CERTIFICATES FOR PAYMENT. § 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 9.5.1.

Appears in 1 contract

Samples: Form of Agreement (Nu Skin Enterprises Inc)

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven three (3) business days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and the Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.

Appears in 1 contract

Samples: Construction Contract (National Instruments Corp /De/)

CERTIFICATES FOR PAYMENT. 20 9.4.1 The Architect will, will within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines recommends is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.

Appears in 1 contract

Samples: www.mohave.edu

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either (1) issue to the Owner a Certificate for Payment to in the Statefull amount of the Application for Payment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her reasons for withholding a Certificate as provided in Subparagraph 9.6.1; or

Appears in 1 contract

Samples: ha.internationaleprocurement.com

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.

Appears in 1 contract

Samples: Form of Agreement

CERTIFICATES FOR PAYMENT. 9.4.1 14.2.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.1Section 14.2.3.

Appears in 1 contract

Samples: teammct.com

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, within seven (7) days after the receipt of the Contractor's completed Application for PaymentPayment and the Architect’s site visit, either either, issue to the Owner a Certificate for Payment to the State, with a copy to the Contractor, for such amount as the Architect determines is properly due, due or notify the Contractor and Owner in writing his or her of the Architect's reasons for withholding a Certificate certification in whole or in part as provided in Subparagraph 9.6.19.5.1.

Appears in 1 contract

Samples: Architectural Services Agreement

CERTIFICATES FOR PAYMENT. 9.4.1 The Architect will, will within seven days after the receipt of the Contractor's completed ’s Application for Payment, either issue to the Owner a Certificate for Payment to the StatePayment, with a copy to the Contractor, for such amount as the Architect determines recommends is properly due, or notify the Contractor and Owner in writing his or her of the Architect’s reasons for withholding a Certificate certification in whole or in part as provided in 10 Subparagraph 9.6.19.5.1.

Appears in 1 contract

Samples: procurement.maricopa.edu