Deemed Termination upon delay Sample Clauses

Deemed Termination upon delay. Without prejudice to the provisions of Clauses 4.2 and 4.3, and subject to the provisions of Clause 9.2, the Parties expressly agree that in the event the Appointed Date does not occur, for any reason whatsoever, within a period of [180 (one hundred and eighty)] days from the Execution Date or the extended period provided in accordance with this Agreement, then all rights, privileges, claims and entitlements of the Concessionaire under or arising out of this Agreement shall be deemed to have been waived by, and to have ceased with the concurrence of the Concessionaire and the Agreement may be terminated by the non-defaulting Party. Provided, however, that in the event the delay in occurrence of the Appointed Date is for reasons attributable to the Concessionaire, the Performance Security or the Bid Security, as the case may be, of the Concessionaire shall be encashed and appropriated by the Authority as Damages thereof.
AutoNDA by SimpleDocs
Deemed Termination upon delay. Without prejudice to the provisions of Clauses 8.3, and subject to the provisions of Clause 7.3, the Parties expressly agree that in the event the Appointed Date does not occur, for any reason whatsoever, within 90 days of signing of the Agreement and submission of the full Performance Security by the Contractor, the Agreement shall be deemed to have been terminated. The Authority shall pay damages to the Contractor equivalent to 1% of the Contract Price (3% in case of standalone bridge projects). All other rights, privileges, claims and entitlements of the Contractor under or arising out of this Agreement shall be deemed to have been waived by, and to have ceased. The Contractor shall hand over all information in relation to the Highway, including but not limited to any data, designs, drawings, structures, information, plans, etc. prepared by them for the Highway, to the Authority. 9 Clause 3.3 may be suitably modified in the event that all the environmental clearances for the Project Highway have been received or are not required. It should be clearly stated that all the environmental clearances for the Project Highway have been received; or such environmental clearances for the Project Highway are not required.
Deemed Termination upon delay. Without prejudice to the provisions of Clauses 8.3, and subject to the provisions of Clause 7.3, the Parties expressly agree that in the event the Appointed Date does not occur, for any reason whatsoever, within 90 days of signing of the Agreement and submission of the full Performance Security by the Contractor, the Agreement shall be deemed to have been terminated. The Authority shall pay damages to the Contractor equivalent to 1% of the Contract Price (3% in case of standalone bridge projects). All other rights, privileges, claims and entitlements of the Contractor under or arising out of this Agreement shall be deemed to have been waived by, and to have ceased. The Contractor shall hand over all information in relation to the Highway, including but not limited to any data, designs, drawings, structures, information, plans, etc. prepared by them for the Highway, to the Authority.
Deemed Termination upon delay. Without prejudice to the provisions of Clauses 8.3, and subject to the provisions of Clause 7.3, the Parties expressly agree that in the event the Appointed Date does not occur, for any reason whatsoever, within 90 days of signing of the Agreement and submission of the full Performance Security by the Contractor, the Agreement shall be deemed to have been terminated. The Authority shall pay damages to the Contractor equivalent to 1% of the Contract Price (3% in case of standalone bridge projects). All other rights, privileges, claims and entitlements of the Contractor under or arising out of this Agreement shall be deemed to have been waived by, and to have ceased. The Contractor shall hand over all information in relation to the Highway, including but not limited to any data, designs, drawings, structures, information, plans, etc. prepared by them for the Highway, to the Authority. 9 Clause 3.3 may be suitably modified in the event that all the environmental clearances for the Project Highway have been received or are not required. It should be clearly stated that all the environmental clearances for the Project Highway have been received; or such environmental clearances for the Project Highway are not required. NH-202 for Package-I (Design Chainage 283+000 Km to 325+440 Km) in the State of Nagaland on EPC mode under NH (O)-NE” MAR 2022
Deemed Termination upon delay. Without prejudice to the provisions of Clauses 3.2, and subject to the provisions of Clause 8.2, the Parties expressly agree that in the event the Appointed Date does not occur, for any reason whatsoever, before 180 (one hundred eighty) days from the date of this Agreement or the extended period provided in accordance with this Agreement, all rights, privileges, claims and entitlements of the Implementation Agency under or arising out of this Agreement shall be deemed to have been waived by, and to have ceased with the concurrence of the Implementation Agency, and the Contract Agreement shall be deemed to have been terminated by mutual agreement of the Parties. Provided, however, that in the event the delay in occurrence of the Appointed Date is for reasons attributable to the Implementation Agency, the Performance Security of the Implementation Agency shall be encashed and appropriated by the Authority as Damages thereof.
Deemed Termination upon delay. 4.2.1 In the event that (i) the Licensee does not procure fulfilment of any or all of the Conditions Precedent set forth in Clause 4.1.3 within a period of 180 (one hundred and eighty) days from the Effective Date, and (ii) the delay has not occurred as a result of failure to fulfil the obligations under Clause 4.1.3 or other breach of this Agreement by the Licensor, or due to Force Majeure, the Licensee shall pay to the Licensor Damages in an amount calculated at the rate of 0.2% (zero point two per cent) of the Performance Security for each day’s delay until the fulfilment of such Conditions Precedent, subject to a maximum amount equal to 20% (twenty percent) of the Performance Security, and upon reaching such maximum, the Licensor may, in its sole discretion, terminate the Agreement.
Deemed Termination upon delay. Without prejudice to the provisions of Clause 4.2 and 4.3, and subject to the provisions of Clause 9.2, the Parties expressly agree that in the event the Appointed Date does not occur, for any reason whatsoever, before the 1st (first) anniversary of the date of this Agreement or the extended period provided in accordance with this Agreement, all rights, privileges, claims and entitlements of the Concessionaire under or arising out of this Agreement shall be deemed to the Concessionaire, and the Concession Agreement shall be deemed to have been terminated by mutual agreement of the Parties. Provided, however, that in the event the delay in occurrence of the Appointed Date is for reasons attributable to the Concessionaire, the Performance Security of the Concessionaire shall be encashed and appropriated by the Authority to the extent of an amount calculated as 1% (one per cent) of the Total Project Cost.
AutoNDA by SimpleDocs
Deemed Termination upon delay. Without prejudice to the provisions of Clauses 4.2 and 4.3, and subject to the provisions of Clause 9.2, the Parties expressly agree that in the event the Appointed Date does not occur, for any reason whatsoever, 120 (one hundred twenty) days from the date of this Agreement or the extended period provided in accordance with this Agreement, all rights, privileges, claims and entitlements of the Aggregator under or arising out of this Agreement shall be deemed to have been waived by, and to have ceased with the concurrence of the Aggregator, and the Pilot Agreement for Procurement of Power - II shall be deemed to have been terminated by mutual agreement of the Parties. Provided, however, that in the event the delay in occurrence of the Appointed Date is for reasons attributable to the Aggregator, the Performance Security of the Aggregator shall be encashed and appropriated by the Utility as Damages thereof.
Deemed Termination upon delay. 4.2.1 In the event that (i) the Operator does not procure fulfilment of any or all of the Conditions Precedent set forth in Article 4.1.2 within a period of ninety (90) days from the ” Handing Over Date, and (ii) the delay has not occurred as a result of failure to fulfil the obligations under Article 4.1.2 or other breach of this Agreement by the Authority, or due to Force Majeure, the Operator shall pay to the Authority, Damages equivalent to an amount calculated at the rate of State Bank of India Prime Lending Rate (SBI PLR) plus 2 % of the Minimum Annual Guarantee for each day’s delay until the fulfilment of such Conditions Precedent, subject to a maximum amount equal to Performance Security and upon reaching such maximum, the Authority may, in its sole discretion, terminate this Agreement.
Deemed Termination upon delay. 4.6.1 Without prejudice to the provisions of Article 4.4 and Article 4.5, and subject to the provisions of Article 9.2, the Parties expressly agree that in the event the Transition Period Conditions as set out in Article 4.2 and Article 4.3 are not completed, for any reason whatsoever, within six months from the Effective Date or the extended period provided in accordance with this Agreement, all rights, privileges, claims and entitlements of the Operator under or arising out of this Agreement shall be deemed to have been waived by, and to have ceased with the concurrence of the Operator, and this Agreement shall be deemed to have been terminated subject to provisions of this Agreement. It is clarified that if the Agreement is terminated because of reasons not attributable to the Operator, the Operator shall be entitled to receive payment for eligible fees for the services provided till the termination of Agreement.