Examples of Project activity in a sentence
Revised Project Schedule submittals shall include a comprehensive listing of all Project activities added or deleted along with a complete listing of all logic and Project activity changes, and, if applicable, any change in the allocation of the Developer’s compensation or price among Project activities.
The WBS for each Project activity shall be defined in terms of work elements reflecting the types of Work.
Project activity durations shall be no longer than sixty (60) days, unless otherwise approved by TxDOT.
No unspecified milestones, Developer-designated constraints, Project float suppression techniques, or use of Project activity durations, logic ties, and/or sequences deemed unreasonable by TxDOT shall be used in any Project Schedule.
Project activity durations shall be in units of whole working days.