Additional Claims. A32.1 No claims for additional payment or time shall be allowed on the grounds of any matter for which a competent contractor would have made due allowance or which the Contractor could reasonably have discovered by a visit to DCLG’s premises, reference to DCLG, or such other means as may have been appropriate.
Appears in 14 contracts
Samples: data.gov.uk, data.gov.uk, data.gov.uk
Additional Claims. A32.1 36.1 No claims for additional payment or time shall be allowed on the grounds of any matter for which a competent contractor would have made due allowance or which the Contractor could reasonably have discovered by a visit to DCLG’s premises, reference to DCLG, or such other means as may have been appropriate.
Appears in 2 contracts
Samples: data.gov.uk, data.gov.uk