Examples of Work Completion Schedule in a sentence
Such unfavorable construction conditions will in no way relieve the Contractor of his responsibility to perform the Works as per the Work Completion Schedule for construction of S/S and associated Line at various location in State of Odisha.
All the mandatory spares covered under the contract shall be supplied along with the main equipment and the delivery would be completed by the respective dates for the various categories of equipment as per the agreed Work Completion Schedule.
The approved Work Completion Schedule submitted by the contractor shall form part of the contract agreement.
The Contractor shall submit Work Completion Schedule conforming to the delivery/erection dates for review and approval of OPTCL.
Similarly for Erection, Installation & Commissioning services including Civil Works shall be executed as per the agreed Work Completion Schedule.
The Bidder shall include in his proposal of program for supplying and erecting the Materials/equipment and associates Civil Works covered under the package/Works in the form of Work Completion Schedule (Bar Chart / PERT) identifying key activities of total work, such as Supply of Materials/Equipment, erection, Installation, Testing & Commissioning of all Materials/Equipment and associated Civil works under the Package/works within the contract completion period.
An advance up to 10% (ten percent) of total contract price (Erection and Commissioning) bearing simple interest @10% p.a. shall be paid as Mobilization Advance, if required, subject to the following.i. Signing of the Contract Agreement along with agreed Work Completion Schedule (PERT/BAR Chart).
Contract Agreement and approved Work Completion Schedule (PERT/BAR Chart).6.2 In the event of any conflict between the above-mentioned documents the matter shall be referred to the OWNER whose decision shall be considered as final and binding upon the parties.
This Contract price break up shall be interlinked with the agreed mile stone of the Work Completion Schedule of the Package.
Contract Agreement and approved Work Completion Schedule (PERT/BAR Chart)6.2 In the event of any conflict between the above-mentioned documents the matter shall be referred to the OWNER whose decision shall be considered as final and binding upon the parties.