Scheduled Acceptance Date definition

Scheduled Acceptance Date has the meaning set forth in Section 4.12.
Scheduled Acceptance Date shall have the meaning specified in Section 2.6(b) of the Participation Agreement.
Scheduled Acceptance Date shall, to the extent applicable, have the meaning specified in the applicable Milestone Performance and Payment Schedule for the corresponding Approved Project, as such Scheduled Acceptance Date may be extended pursuant to this Agreement.

Examples of Scheduled Acceptance Date in a sentence

  • If the Scheduled Acceptance Date is subject to adjustment in accordance with this Section 5.5.3, the Scheduled Acceptance Date shall be extended by the number of days that the Manager can reasonably demonstrate to the County’s Authorized Representative are directly attributable to the effects of such County Fault.

  • If the Scheduled Acceptance Date is subject to an adjustment in accordance with this Section 5.5.3.1, the Scheduled Acceptance Date shall be extended by the number of Day(s) that the Manager can reasonably demonstrate to the County that are directly attributable to the Uncontrollable Circumstance.

  • The time impact analyses described in Section 1.3.8 (Time Impact Analysis) of this Appendix are very important submittals to the SRWA and shall be utilized to evaluate activity durations and the relationships between activities before deciding on possible changes to the Scheduled Acceptance Date or the date for achievement of Final Completion, and viable options to mitigate time impacts.

  • When Design and Construction Requirement Changes are initiated, delays are experienced, or the Company desires to revise the schedule logic, the Company shall submit to the SRWA a written time impact analysis illustrating the influence of each change, delay, or Company request on the Scheduled Acceptance Date or the achievement of Final Completion.

  • In the event that any requested test, observation or inspection causes a material delay in the construction schedule, the Scheduled Acceptance Date shall be adjusted to reflect the actual period of time needed for completion as directly caused by the requested testing, but only if such testing, observation or inspection does not reveal any material failure or non-compliance as set forth herein.


More Definitions of Scheduled Acceptance Date

Scheduled Acceptance Date means the day [ ]consecutive calendar days following the Contract Date [as proposed on Proposal Form 12] or, in the event of one or more delays caused by Uncontrollable Circumstances during the Design-Build Period, (2) Change Orders during the Design-Build Period, or (3) the election of the Owner to direct the timing of the commencement of the Acceptance Test pursuant to Section 4.6 (Owner Right to Direct the Timing of the Commencement of the Acceptance Test), the date which is the next Business Day following the date calculated by adding to the Scheduled Acceptance Date the aggregate number of days of such delay. Any such extension in the Scheduled Acceptance Date shall be evidenced by a Contract Administration Memorandum or Change Order, as appropriate.
Scheduled Acceptance Date means the date which is 1,347 days following the issuance of the Notice to Proceed with the Development Period by the BWS, as such Scheduled Acceptance Date may be adjusted due to the occurrence of Uncontrollable Circumstances.
Scheduled Acceptance Date means the day 778 consecutive calendar days following the date of issuance of the Notice to Proceed, as adjusted due to delay caused by Uncontrollable Circumstances, City Fault or by a City-requested Change Order.
Scheduled Acceptance Date means , 2022 [this will be a date that is 1,150 days after the Contract Date] or such other Scheduled Acceptance Date as may be approved by Change Order.
Scheduled Acceptance Date means the date falling on the 1 (one) year after issue of the Notice of Readiness under Clause 5.1, as it may be postponed under Clause 5.5.
Scheduled Acceptance Date means the date falling ***** days after the Scheduled Delivery Date.
Scheduled Acceptance Date means, in relation to: