Rescheduling of Tests Sample Clauses

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
AutoNDA by SimpleDocs
Rescheduling of Tests. If the Independent Expert certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering Hospitality Services or issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire at its own cost and expense, shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. The provisions of this Article 14.2 shall apply mutatis mutandis to such re-scheduled Tests.
Rescheduling of Tests. If the Independent Engineer certifies to CEB and Seller that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the tests could not be held or had to be suspended, Seller shall be entitled to re-schedule the tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. If the Commissioning Committee certifies to Railways and the SPD that it is unable to issue the Completion Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the SPD shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. If the Independent Engineer certifies to TANGEDCO and the Mine Developer and Operator that because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Mine Developer and Operator shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. Provided, however, that the Mine Developer and Operator shall be excused for the delay in Tests arising hereunder if such delay is not solely attributable to the Mine Developer and Operator. ******
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. to km 34.039 to 2-Lane under SARDP-NE “Phase-A” in the state of Meghalaya on EPC mode (Package-I) June 2021
Rescheduling of Tests. 13 Change of Scope Drafit Contract Agreement 13.1 Change of Scope
AutoNDA by SimpleDocs
Rescheduling of Tests. 13 Change of Scope
Rescheduling of Tests. 14.6.1 If the Independent Engineer or the Monitoring Agency, as the case may be, certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering Diagnostic Services and OPD Services or issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Completion Tests could not be held or had to be suspended, the Concessionaire at its own cost and expense, shall be entitled to re-schedule the Completion Tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. Contract AgreementPage 82 of 149 “Development and Up-gradation of 4 laning of Jamugurihat to end of Biswanath Chariali By-Pass from Km 182.000 to Km 208.000 of NH -52 in the state of Assam in Engineering, Procurement & Construction (EPC) basis. ” Jan 2023 Article 13 Change of Scope 13.1 Change ofScope (i) The Authority may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/ alterations to the Works (“Change of Scope”) within a period of six months counted from the Appointed Date. Upon the Authority making its intention known to the Contractor for the specific Change of Scope, be it positive or negative, the Contractor shall submit his proposal for the said Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article13. (ii) Provided that any such Change of Scope, excluding major structures (e.g. Major Bridge/ ROB/ RUB/ Flyover/ elevated road of more than 50 m length) may be required and agreed to be executed between the parties beyond the period of six months of the Appointed Date but before expiry of 50% of the original Scheduled Construction Period of the Project Highway, subject to the condition that it shall not entail any claims (e.g. Extension of Time/ Prolongation related claims), against the Authority. (iii) The Change of Scope shall mean thefollowing: (a) change in specifications of any item ofWorks; (b) omission of any work from the Scope of the Project except under Clause 8.3 (iii); provided that, subject to Clause 13.5, the Authority shall not omit any Work under this Clause in order to get it executed by any other authority;and / or (c) any additional Work, Plant, Materials or services which are not included in the Scope of the Project, including any associated Tests on completion of construction. 13.2