Recovery Schedule definition

Recovery Schedule has the meaning set forth in Section 5.5.
Recovery Schedule means the schedule to recover schedule delays that the Developer is required to prepare under Section 10.6 of the Agreement and Exhibit G to the Agreement.
Recovery Schedule has the meaning given in Schedule 12 – Works Scheduling Requirements.

Examples of Recovery Schedule in a sentence

  • Prior to exercising any remedy of termination under Section 21, TxDOT shall provide Developer with a reasonable opportunity to develop a Recovery Schedule to make-up the delay.

  • All costs incurred by Developer in preparing and achieving the Recovery Schedule shall be borne by Developer and shall not result in a change to Developer’s compensation or price.

  • Developer may invoice TxDOT for any amounts withheld pursuant to this Section 10.6.1 at any time after approval of a Recovery Schedule by TxDOT.

  • If a Recovery Schedule is required under this Section 10.6.1, Developer shall have the right to receive only 75% of the amount of each milestone payment, if any, until such time as Developer has prepared and TxDOT has approved such Recovery Schedule.

  • Each Recovery Schedule shall be subject to TxDOT’s written approval.


More Definitions of Recovery Schedule

Recovery Schedule means the schedule Design-Builder is required to provide under Volume 3-Technical Provisions, Document 1- General Requirements, Section 4.8.1.
Recovery Schedule means a schedule created pursuant to section 2.3.17 specifically, which clearly and realistically identifies adjustments proposed to bring the Project back to the initial project Substantial Completion date.
Recovery Schedule means a schedule created pursuant to section 2.4 generally, and section 2.4.5.9 specifically, which clearly and realistically identifies adjustments proposed to bring the Project back to the initial project Substantial Completion date.
Recovery Schedule means a schedule, meeting all requirements of Article 8 of the General Conditions, generated by Contractor and which shall identify the correction, acceleration or extraordinary efforts to be taken by Contractor and its work forces to recapture the contract Milestone Dates.
Recovery Schedule has the meaning set forth in Section 3.8.5.
Recovery Schedule means a schedule and narrative report that demonstrates XXXX Firm’s proposed plan to regain lost schedule progress and achieve the Milestones by the applicable Milestone Deadline and which complies with the requirements of Section 9.6.
Recovery Schedule has the meaning given in Section 5.1 of Schedule 3 [Construction Schedule].